14.—(1) No part of the authorised development may commence until a construction worker travel plan has been submitted to and approved by the relevant planning authority in consultation with the highway authority. The construction worker travel plan must be in accordance with the travel plan (other than the measures which relate to the operational phase).
(2) The construction worker travel plan must be carried out as approved.