Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
12.—(1) No part of authorised development comprised in numbered work 1 may commence until a written scheme (which may be included in the construction environment management plan) to deal with the contamination of any land, including groundwater, within the Order limits which is likely to cause significant harm to persons or significant pollution of controlled waters or ground waters or the environment has been submitted to and approved by the relevant planning authority in consultation with the Environment Agency.
(2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by the relevant planning authority, to identify the extent of any contamination and a remediation strategy identifying the remedial measures to be taken, if required, to render the land fit for its intended purpose, together with a management plan (as necessary) which sets out long-term measures with respect to any contaminants remaining on the site and a verification plan outlining how achieving the remedial objectives will be demonstrated.
(3) Remediation, if required, must be carried out in accordance with the scheme approved under sub-paragraph (1).
(4) A verification report demonstrating completion of any remediation works and the effectiveness of the remediation must be submitted to and approved, in writing, by the local planning authority in consultation with the Environment Agency.
Commencement Information
I1Sch. 2 para. 12 in force at 14.8.2015, see art. 1
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: