11.—(1) No part of the authorised development shall be commenced until a construction environment management plan covering that numbered work has been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency. The final construction environment management plan must be in accordance with the outline construction environment management plan and must include the following—
(a)complaints procedures;
(b)provision for setting up a Community Liaison Group;
(c)nuisance management including measures to avoid or minimise the impacts of construction works (covering dust, noise and vibration);
(d)waste management;
(e)an assessment of the site specific risks to and mitigation measures designed to protect controlled waters (surface and groundwaters) including pollution incident control;
(f)landscape and visual impact mitigation (specifically the protection of trees and hedgerows to be retained in accordance with BS 5837: 2012 (or its updates) and a scheme to minimise visual intrusion of the construction works);
(g)security measures;
(h)protocol in relation to unexploded ordnance;
(i)save in respect of numbered work 1, a protocol in the event that unexpected contaminated land is identified during ground investigation or construction;
(j)restoration of site following completion of construction;
(k)the requirement for completion of a soil resources survey, details of methods for soil handling, storage and replacement during construction and details of the aftercare programme; and
(l)a scheme of artificial lighting.
(2) All construction works must be undertaken in accordance with the approved construction environment management plan.