The Progress Power (Gas Fired Power Station) Order 2015

Maintenance of authorised developmentE+W

4.  The undertaker may at any time maintain the authorised development, except to the extent that this Order or an agreement made under this Order provides otherwise.

Commencement Information

I1Art. 4 in force at 14.8.2015, see art. 1