SCHEDULES

SCHEDULE 8PROTECTIVE PROVISIONS

PART 1PROTECTION FOR NETWORK RAIL

I117

In the assessment of any sums payable to Network Rail under this Part of this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by LUL under this Part of this Schedule or increasing the sums so payable.