1. The following provisions of the principal Act apply to the matters which are the subject of this Order on the general assumptions mentioned in paragraph 2 and, where any special assumption is mentioned in paragraph 3 for any such provision, on the special assumptions for it so mentioned—
(a)sections 8 (extinguishment of private rights of way), 9 (extinguishment of rights of statutory undertakers etc), 10 (planning: general), 11 (permitted developments: time limit), 12 (fees for planning applications), 13 (power to disapply section 10(1)), 15 (extension of permitted development rights) and section 20 (control of construction sites: appeals);
(b)paragraphs 8 (discharge of water) and 9 (entry for preparatory purposes) of Schedule 2 (works: further and supplementary provisions);
(c)paragraphs 1 (stopping up), 2, 3, 5(1) to 5(3) (temporary interference), 6 (working sites in highways), 7, 8 (street works), 9, 10 (construction), 11 (maintenance), 14 (agreements with highway authorities etc) and 15(1) (use of subsoil) of Schedule 3 (highways);
(d)paragraphs 3, 4 and 6 to 11 of Part 2 (development in the area of a unitary authority), and paragraphs 28 to 37 of Part 4 (supplementary) of Schedule 7 (planning conditions);
(e)paragraphs 14 to 17 of Schedule 14 (disapplication and modification of miscellaneous controls);
(f)parts 1 (protection of highways and traffic), 2 (protection for electricity, gas, water and sewerage undertakers) and 4 (protection of electronic communications code networks) of Schedule 17 (protective provisions).