8.—(1) The promoter may acquire compulsorily so much of the land shown on the works and land plan within the limits of deviation as land to be acquired compulsorily and described in the book of reference as may be required for the purposes of the authorised works and may use any land so acquired for those purposes or for any other purposes that are ancillary to the promoter’s statutory undertaking.
(2) This article is subject to article 12 (acquisition of land limited to subsoil lying more than 9 metres beneath surface) and article 13 (temporary use of land for construction of works).