PART 2Principal powers

Defence to proceedings in respect of statutory nuisanceI19

1

Where proceedings are brought under section 82(1) of the Environmental Protection Act 199014 (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraph (g) of section 79(1) of that Act (noise emitted from premises so as to be prejudicial to health or a nuisance) no order may be made, and no fine may be imposed, under section 82(2) of that Act if the condition set out in paragraph (2) has been satisfied.

2

The condition to be satisfied for the purposes of paragraph (1) is that the defendant shows that the nuisance relates to premises used by the undertaker for the purposes of or in connection with the construction of the authorised project and that the nuisance is attributable to the carrying out of the authorised project in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site) or 65 (noise exceeding registered level), of the Control of Pollution Act 197415.

3

Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project.

4

The application to the authorised project of section 158 of the 2008 Act (nuisance: statutory authority) or any rule of law having similar effect does not extend to confer upon the undertaker the protection afforded by section 158 of the 2008 Act in respect of any nuisance arising from noise attributable to the use of the authorised project.