xmlns:atom="http://www.w3.org/2005/Atom"

Circumstances relating to certain delays in grid or radar works in the case of generating stations accredited on or before 31st March 2017

5.—(1) The circumstances set out in this article are where the electricity is—

(a)generated by a generating station which was accredited on or before 31st March 2017, and

(b)generated using 2017/18 capacity in respect of which the documents specified in paragraph (2), (3) or (4) have been submitted by the operator of the station to the Authority.

(2) The documents specified in this paragraph are—

(a)evidence of an agreement with a network operator (“the relevant network operator”) to carry out grid works in relation to the station (“the relevant grid works”);

(b)a copy of a document written by, or on behalf of, the relevant network operator which estimated or set a date for completion of the relevant grid works (“the planned grid works completion date”) which was no later than 31st March 2017;

(c)a letter from the relevant network operator confirming (whether or not such confirmation is subject to any conditions or other terms) that—

(i)the relevant grid works were completed after the planned grid works completion date, and

(ii)in the relevant network operator’s opinion, the failure to complete the relevant grid works on or before the planned grid works completion date was not due to any breach by a generating station developer of any agreement with the relevant network operator; and

(d)a declaration by the operator of the generating station that, to the best of their knowledge and belief, the 2017/18 capacity would have formed part of the station on or before 31st March 2017 if the relevant grid works had been completed on or before the planned grid works completion date.

(3) The documents specified in this paragraph are—

(a)evidence of an agreement between a generating station developer and a person who is not a generating station developer (“the radar works agreement”) for the carrying out of radar works (“the relevant radar works”);

(b)a copy of a document written by, or on behalf of, a party to the radar works agreement (other than a generating station developer) which estimated or set a date for completion of the relevant radar works (“the planned radar works completion date”) which was no later than 31st March 2017;

(c)a letter from a party to the radar works agreement (other than a generating station developer) confirming, whether or not such confirmation is subject to any conditions or other terms, that—

(i)the relevant radar works were completed after the planned radar works completion date, and

(ii)in that party’s opinion, the failure to complete the relevant radar works on or before the planned radar works completion date was not due to any breach of the radar works agreement by a generating station developer; and

(d)a declaration by the operator of the generating station that, to the best of their knowledge and belief, the 2017/18 capacity would have formed part of the station on or before 31st March 2017 if the relevant radar works had been completed on or before the planned radar works completion date.

(4) The documents specified in this paragraph are—

(a)the documents specified in paragraph (2)(a), (b) and (c);

(b)the documents specified in paragraph (3)(a), (b) and (c); and

(c)a declaration by the operator of the generating station that, to the best of their knowledge and belief, the 2017/18 capacity would have formed part of the station on or before 31st March 2017 if—

(i)the relevant grid works had been completed on or before the planned grid works completion date, and

(ii)the relevant radar works had been completed on or before the planned radar works completion date.

(5) In this article—

“2017/18 capacity”, in relation to a generating station, means any generating capacity—

(a)

which does not form part of the original capacity of the station, and

(b)

which, in the Authority’s view, first formed part of the station from a date no earlier than 1st April 2017 and no later than 31st March 2018; and

“generating station developer”, in relation to a generating station, means the operator of the station, or a person who arranged for the construction of the 2017/18 capacity of the station.