PART 3ACQUISITION AND POSSESSION OF LAND

Temporary possession of land

Temporary use of land for maintaining authorised project36

1

Subject to paragraph (2) the undertaker may—

a

enter on and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised project;

b

enter on any land within the Order limits for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised project; and

c

construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

2

Paragraph (1) shall not authorise the undertaker to take temporary possession of—

a

any house or garden belonging to a house; or

b

any building (other than a house) if it is for the time being occupied.

3

Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land. Such notice shall include details of the proposed works.

4

The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised project for which possession of the land was taken.

5

Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

6

The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

7

Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

8

Nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act (further provisions as to compensation for injurious affection) or under any other enactment in respect of loss or damage arising from the maintenance of the authorised project, other than loss or damage for which compensation is payable under paragraph (6).

9

Where the undertaker takes possession of land under this article, the undertaker shall not be required to acquire the land or any interest in it.

10

Section 13 of the 1965 Act (refusal to give possession to acquiring authority) shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).