PART 2WORKS PROVISIONS

Streets and traffic regulations

Agreements with street authorities17

1

The undertaker may enter into agreements with a street authority or (in the case of a city walkway) the city walkway authority with respect to—

a

the construction of any new street or city walkway including any structure carrying the street or city walkway whether or not over or under any part of the authorised project;

b

the strengthening, improvement, repair or reconstruction of any street or city walkway under the powers conferred by this Order;

c

any stopping up, alteration or diversion of a street or city walkway authorised by this Order;

d

the carrying out in the street of any of the works referred to in article 10(1) (street works) or their maintenance;

e

the alteration of any street further to article 11(1) or (2) (power to alter the layout etc of streets); or

f

such other works as the parties may agree.

2

Such an agreement may, without prejudice to the generality of paragraph (1)—

a

make provision for the street authority or the city walkway authority to carry out any function under this Order which relates to the street in question;

b

include an agreement between the undertaker and street authority or the city walkway authority specifying a reasonable time for completion of the works;

c

provide for the dedication of any new street as public highway further to section 38 of the 1980 Act;

d

provide for any new way to be declared as city walkway in accordance with the City of London (Various Powers) Act 1967;

e

contain such terms as to payment as the parties consider appropriate; and

f

contain such other terms as the parties may agree between them.