SCHEDULE 10Deemed licence under the Marine and Coastal Access Act 2009 – generation assets

PART 2Conditions

Pre-construction plans and documentation13

1

Each programme, statement, plan, protocol or scheme required to be approved under condition 11 must be submitted for approval at least four months prior to the intended start of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.

2

No licensed activities shall commence until the MMO has approved in writing each programme, statement, plan, protocol or scheme required to be approved under condition 11 and the licensed activities must be carried out in accordance with the approved plans, protocols, statements, schemes and details approved under condition 11, unless otherwise agreed in writing by the MMO.