Search Legislation

The Croxley Rail Link Order 2013

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

50.  The Council must repay to LUL all reasonable costs, charges and expenses reasonably incurred by LUL—

(a)in constructing any part of a specified work on behalf of the Council as provided by paragraph 40 or in constructing any protective works under the provisions of paragraph 41, including, in respect of any permanent protective works, a capitalised sum representing the cost which may be expected to be reasonably incurred by LUL in maintaining and renewing such works;

(b)in respect of the employment or procurement of the services of any inspectors, supervisory staff, signallers, watchkeepers and other persons appointed for inspecting, monitoring, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of the specified works and to ensure the continued safe and efficient operation of LUL’s railway undertaking (including any relocation of works, apparatus and equipment necessitated by the specified works) and the comfort and safety of passengers;

(c)in respect of any special traffic working resulting from any speed restrictions which may, in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of the specified works or from the substitution or diversion of railway services of LUL which may be reasonably necessary for the same reason;

(d)in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or consequence of the construction or failure of the specified works; and

(e)in respect of the approval of plans and any supervision by the engineer of the construction of the specified works.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources