The North Blyth Biomass Power Station Order 2013

Aviation safety

26.  That part of the authorised development comprising the main stack may not commence until there has been submitted to and approved in writing by the relevant planning authority following consultation with the Civil Aviation Authority a scheme for the provision of safety lighting on the stack forming part of the authorised development. The authorised development must be carried out in accordance with the approved scheme and the lighting required by such scheme must at all times be maintained to the reasonable satisfaction of the relevant planning authority.