PART 2Subsystems
F1Application for exemptions14A
1
Where a project entity applies for an exemption under regulation 14, they must apply to the Competent Authority in writing.
2
The following information must be included in the application for an exemption—
a
a description of the work, goods and services subject to the exemption, specifying the key dates, the location, and the operational and technical area;
b
a precise reference to the NTSN (or its parts) from which an exemption is sought;
c
a precise reference to, and details of, the alternative provisions which will be applied;
d
for requests made under regulation 14(2)(a), evidence in support of the fact that the project is at an advanced stage of development;
e
for requests made under regulation 14(2)(f), information which outlines how the solution deviates from or complements the applicable NTSNs;
f
justification of the exemption, including the main reasons of a technical, economic, commercial, operational and/or administrative nature; and
g
any other information justifying the application for an exemption.
3
After receipt of the information specified in paragraph (2), the Competent Authority must determine the application for an exemption.
4
When the Competent Authority has made a determination it must inform the applicant of that determination.
5
When the Competent Authority makes a determination of a case under regulation 14(2)(f) (innovative solutions), and informs the applicant of the outcome of the application, the Competent Authority must also publish its determination.