Search Legislation

The Town and Country Planning (Environmental Impact Assessment) Regulations 2011

Status:

This is the original version (as it was originally made).

Regulation 2(1)

SCHEDULE 1Descriptions of development for the purposes of the definition of “Schedule 1 development”

This schedule has no associated Explanatory Memorandum

Interpretation

In this Schedule—

“airport” means an airport which complies with the definition in the 1944 Chicago Convention setting up the International Civil Aviation Organisation (Annex 14)(1);

“express road” means a road which complies with the definition in the European Agreement on Main International Traffic Arteries of 15 November 1975(2);

“nuclear power station” and “other nuclear reactor” do not include an installation from the site of which all nuclear fuel and other radioactive contaminated materials have been permanently removed; and development for the purpose of dismantling or decommissioning a nuclear power station or other nuclear reactor shall not be treated as development of the description mentioned in paragraph 2(b) of this Schedule.

Descriptions of development

The carrying out of development to provide any of the following—

1.  Crude-oil refineries (excluding undertakings manufacturing only lubricants from crude oil) and installations for the gasification and liquefaction of 500 tonnes or more of coal or bituminous shale per day.

2.   

(a)Thermal power stations and other combustion installations with a heat output of 300 megawatts or more; and

(b)Nuclear power stations and other nuclear reactors (except research installations for the production and conversion of fissionable and fertile materials, whose maximum power does not exceed 1 kilowatt continuous thermal load).

3.   

(a)Installations for the reprocessing of irradiated nuclear fuel;

(b)Installations designed—

(i)for the production or enrichment of nuclear fuel,

(ii)for the processing of irradiated nuclear fuel or high-level radioactive waste,

(iii)for the final disposal of irradiated nuclear fuel,

(iv)solely for the final disposal of radioactive waste,

(v)solely for the storage (planned for more than 10 years) of irradiated nuclear fuels or radioactive waste in a different site than the production site.

4.   

(a)Integrated works for the initial smelting of cast-iron and steel;

(b)Installations for the production of non-ferrous crude metals from ore, concentrates or secondary raw materials by metallurgical, chemical or electrolytic processes.

5.  Installations for the extraction of asbestos and for the processing and transformation of asbestos and products containing asbestos—

(a)for asbestos-cement products, with an annual production of more than 20,000 tonnes of finished products;

(b)for friction material, with an annual production of more than 50 tonnes of finished products; and

(c)for other uses of asbestos, utilisation of more than 200 tonnes per year.

6.  Integrated chemical installations, that is to say, installations for the manufacture on an industrial scale of substances using chemical conversion processes, in which several units are juxtaposed and are functionally linked to one another and which are—

(a)for the production of basic organic chemicals;

(b)for the production of basic inorganic chemicals;

(c)for the production of phosphorous-, nitrogen- or potassium-based fertilisers (simple or compound fertilisers);

(d)for the production of basic plant health products and of biocides;

(e)for the production of basic pharmaceutical products using a chemical or biological process;

(f)for the production of explosives.

7.   

(a)Construction of lines for long-distance railway traffic and of airports with a basic runway length of 2,100 metres or more;

(b)Construction of motorways and express roads;

(c)Construction of a new road of four or more lanes, or realignment and/or widening of an existing road of two lanes or less so as to provide four or more lanes, where such new road, or realigned and/or widened section of road would be 10 kilometres or more in a continuous length.

8.   

(a)Inland waterways and ports for inland-waterway traffic which permit the passage of vessels of over 1,350 tonnes;

(b)Trading ports, piers for loading and unloading connected to land and outside ports (excluding ferry piers) which can take vessels of over 1,350 tonnes.

9.  Waste disposal installations for the incineration, chemical treatment (as defined in Annex IIA to Council Directive 75/442/EEC(3) under heading D9), or landfill of hazardous waste as defined in regulation 6 of the Hazardous Waste (England and Wales) Regulations 2005(4).

10.  Waste disposal installations for the incineration or chemical treatment (as defined in Annex IIA to Council Directive 75/442/EEC under heading D9) of non-hazardous waste with a capacity exceeding 100 tonnes per day.

11.  Groundwater abstraction or artificial groundwater recharge schemes where the annual volume of water abstracted or recharged is equivalent to or exceeds 10 million cubic metres.

12.   

(a)Works for the transfer of water resources, other than piped drinking water, between river basins where the transfer aims at preventing possible shortages of water and where the amount of water transferred exceeds 100 million cubic metres per year;

(b)In all other cases, works for the transfer of water resources, other than piped drinking water, between river basins where the multi-annual average flow of the basin of abstraction exceeds 2,000 million cubic metres per year and where the amount of water transferred exceeds 5% of this flow.

13.  Waste water treatment plants with a capacity exceeding 150,000 population equivalent as defined in Article 2 point (6) of Council Directive 91/271/EEC(5).

14.  Extraction of petroleum and natural gas for commercial purposes where the amount extracted exceeds 500 tonnes per day in the case of petroleum and 500,000 cubic metres per day in the case of gas.

15.  Dams and other installations designed for the holding back or permanent storage of water, where a new or additional amount of water held back or stored exceeds 10 million cubic metres.

16.  Pipelines with a diameter of more than 800 millimetres and a length of more than 40 kilometres:

  • for the transport of gas, oil, chemicals, or

  • for the transport of carbon dioxide streams for the purposes of geological storage, including associated booster stations.

17.  Installations for the intensive rearing of poultry or pigs with more than—

(a)85,000 places for broilers or 60,000 places for hens;

(b)3,000 places for production pigs (over 30 kg); or

(c)900 places for sows.

18.  Industrial plants for—

(a)the production of pulp from timber or similar fibrous materials;

(b)the production of paper and board with a production capacity exceeding 200 tonnes per day.

19.  Quarries and open-cast mining where the surface of the site exceeds 25 hectares, or peat extraction where the surface of the site exceeds 150 hectares.

20.  Installations for storage of petroleum, petrochemical or chemical products with a capacity of 200,000 tonnes or more.

21.  Any change to or extension of development listed in this Schedule where such a change or extension in itself meets the thresholds, if any, or description of development set out in this Schedule.

22.  Storage sites pursuant to Directive 2009/31/EC of the European Parliament and of the Council of 23 April 2009 on the geological storage of carbon dioxide.(6)

23.  Installations for the capture of carbon dioxide streams for the purposes of geological storage pursuant to Directive 2009/31/EC from installations covered by this Schedule, or where the total yearly capture of carbon dioxide is 1.5 megatonnes or more.

(1)

See Command Paper 6614.

(2)

See Command Paper 6993.

(3)

O.J. No. L 194, 25.7.1975, p. 39. Council Directive 75/442/EEC was amended by Council Directive 91/156/EEC (O.J. No. L 78, 26.3.1991, p. 32) and by Commission Decision 94/3/EC (O.J. No. L 5, 7.1.1994, p. 15).

(5)

O.J. No. L 135, 30.5.1991, p. 40.

(6)

O. J. No L 140, 5.6.2009, p. 114.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources