Submission of documents and information to the examiner

This section has no associated Explanatory Memorandum

19.—(1) The charging authority must submit the following to the examiner (in addition to the declaration required under section 212(4) of PA 2008)—

(a)the draft charging schedule;

(b)a statement setting out—

(i)if representations were made in accordance with regulation 17, the number of representations made and a summary of the main issues raised by the representations, or

(ii)that no such representations were made;

(c)copies of any representations made in accordance with regulation 17;

(d)where the charging authority modified the draft charging schedule after it was published in accordance with regulation 16, a statement of modifications; and

(e)copies of the relevant evidence.

(2) Of the documents and statements mentioned in paragraph (1)—

(a)a copy of each must be sent in paper form; and

(b)a copy of those mentioned in paragraph (1)(a), (b) and (d) and, to the extent that it is practicable to do so, of those mentioned in paragraph (1)(c) and (e), must be sent electronically.

(3) As soon as practicable after a charging authority submits a draft charging schedule to the examiner it must—

(a)make available at the places where the documents mentioned in regulation 16(1)(a) were made available, a copy of the draft charging schedule and of each of the documents mentioned in paragraph (1);

(b)publish on its website—

(i)the draft charging schedule and the documents mentioned in paragraph (1)(a), (b) and (d),

(ii)any of the documents mentioned in paragraph (1)(c) and (e) which it is practicable to so publish, and

(iii)a statement of the fact that a copy of the draft charging schedule and of each of the documents mentioned in paragraph (1) are available for inspection and of the places at which they can be inspected; and

(c)give notice to those persons who requested to be notified of the submission of the draft charging schedule to the examiner that the draft has been so submitted.

(4) Where the charging authority modified the draft charging schedule after it was published in accordance with regulation 16, the charging authority must send a copy of the statement of modifications to each of the persons invited to make representations under regulation 15.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources