Regulation 5
SCHEDULE 1PROVISIONS TO BE INCLUDED IN A LICENCE
This schedule has no associated Explanatory Memorandum
Grant of a storage permit
1. If a storage permit is granted under a licence then, subject to regulation 12, paragraphs 2, 3 and 4 of this Schedule apply in respect of the storage site authorised under that storage permit.
Closure of storage site by the operator
2.—(1) The operator must close the storage site where the conditions mentioned in regulation 8(1)(k) are met.
(2) The operator may close the storage site if—
(a)the consent of the authority has been given following an application under sub-paragraph (3), and
(b)any conditions attached to that consent have been met.
(3) An application for the authority’s consent to the closure of the storage site must—
(a)be made in writing and sent to the Department of Energy and Climate Change, and
(b)contain the reasons why the operator proposes to close the storage site.
(4) However, a storage site may not be closed under sub-paragraph (1) or (2) until the terms of the post-closure plan have been determined under regulation 13(3).
Post-closure plan
3.—(1) Prior to the closure of the storage site in accordance with paragraph 1(1) or (2) of this Schedule, the operator must submit a proposed post-closure plan to the authority for approval.
(2) That proposal must be based on the provisional post-closure plan, subject to any modifications proposed by the operator.
(3) In deciding whether to propose any such modifications, the operator must take into account—
(a)an analysis of the relevant risks;
(b)current best practice; and
(c)any improvements in the available technology.
Post-closure obligations
4.—(1) After the storage site has been closed and until the licence is terminated, the operator must continue to—
(a)monitor the storage site in accordance with paragraph 2 of Schedule 2,
(b)comply with its reporting and notification obligations in accordance with paragraph 3 of Schedule 2 (with the exception of sub-paragraph (5)(b)), and
(c)comply with its obligations to take corrective measures in accordance with paragraph 6 of Schedule 2.
(2) However, for those purposes any reference to the monitoring plan or the corrective measures plan is to be read as a reference to the post-closure plan.
(3) The operator must seal the storage site and remove the injection facilities in accordance with its obligations under Part 4 of the Petroleum Act 1998.
Extraction of stored CO2
5. The operator must not (and must not permit any other person to) extract stored CO2 from the storage site except with the prior written consent of the authority and in accordance with any conditions subject to which any such consent is given.