- Latest available (Revised)
- Original (As made)
There are multiple versions of this provision on screen. These apply to different geographical extents.
The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.
The Building Regulations 2010, Section 18 is up to date with all changes known to be in force on or before 14 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
18.—(1) This regulation applies where it appears to a [F1relevant authority] that unauthorised building work has been carried out on or after 11th November 1985.
(2) Where this regulation applies, the owner (in this regulation referred to as “the applicant”) may apply in writing to the [F2relevant authority] for a regularisation certificate in accordance with this regulation, and shall send with the application—
(a)a statement that the application is made in accordance with this regulation,
(b)a description of the unauthorised work,
(c)so far as is reasonably practicable, a plan of the unauthorised work, and
(d)so far as is reasonably practicable, a plan showing any additional work required to be carried out to secure that the unauthorised work complies with the requirements relating to building work in the building regulations which were applicable to that work when it was carried out (in this regulation referred to as “the relevant requirements”).
(3) Where a [F3relevant authority] receive an application in accordance with this regulation, they may require the applicant to take such reasonable steps, including laying open the unauthorised work for inspection by the authority, making tests and taking samples, as the authority think appropriate to ascertain what work, if any, is required to secure that the relevant requirements are met.
(4) When the applicant has taken any such steps required by the [F4relevant authority] as are described in paragraph (3), and having had regard to any direction given in accordance with sections 8 and 9 of, and Schedule 2 to, the Act dispensing with or relaxing a requirement in building regulations which applies to the unauthorised work, the [F4relevant authority] shall notify the applicant—
(a)of the work which in their opinion is required to comply with the relevant requirements or those requirements as dispensed with or relaxed, or
(b)that they cannot determine what work is required to comply with the relevant requirements or those requirements as dispensed with or relaxed, or
(c)that no work is required to secure compliance with the relevant requirements or those requirements as dispensed with or relaxed.
(5) Where the [F5relevant authority] have been able to satisfy themselves, after taking all reasonable steps for that purpose that—
(a)the relevant requirements have been satisfied (taking account of any work carried out and any dispensation or relaxation given in accordance with sections 8 and 9 of, and Schedule 2 to, the Act), or
(b)no work is required to secure that the unauthorised work satisfies the relevant requirements (taking account of any such dispensation or relaxation),
they may give a certificate to that effect (in this regulation referred to as “a regularisation certificate”).
(6) A regularisation certificate shall be evidence (but not conclusive evidence) that the relevant requirements specified in the certificate have been complied with.
[F6(6A) Where the relevant authority is the regulator, it must send a copy of each certificate it gives under this regulation in relation to a building to the local authority for the area in which the building is situated.]
(7) Where this regulation applies, regulations 12 and 14 shall not apply, and neither the supply of plans nor the taking of any other action in accordance with this regulation is to be treated [F7as an application for building control approval with full plans] in accordance with building regulations.
[F8(8) In this regulation “unauthorised building work”—
(a)where the relevant authority is the local authority, means building work, other than work in relation to which an initial notice, an amendment notice, a public body’s notice or a regulator’s notice has effect, which is done without—
(i)a building notice being given to the local authority;
(ii)an application for building control approval with full plans of the work being given to the local authority; or
(iii)a notice of intention to start work being given to the local authority, in accordance with regulation 16(1), where a building notice has been given or an application for building control approval with full plans of the work has been given;
(b)where the relevant authority is the regulator, means building work which is work in relation to which a regulator’s notice has effect but which is done without—
(i)a building notice being given to the regulator;
(ii)an application for building control approval with full plans of the work being given to the regulator; or
(iii)a notice of intention to start work being given to the regulator, in accordance with regulation 16(1), where a building notice has been given or an application for building control approval with full plans of the work has been given.]
Extent Information
E1This version of this provision applies to England only; a separate version has been created for Wales only
Textual Amendments
F1Words in reg. 18(1) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(a) (with regs. 22-24)
F2Words in reg. 18(2) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(a) (with regs. 22-24)
F3Words in reg. 18(3) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(a) (with regs. 22-24)
F4Words in reg. 18(4) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(a) (with regs. 22-24)
F5Words in reg. 18(5) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(a) (with regs. 22-24)
F6Reg. 18(6A) inserted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(b) (with regs. 22-24)
F7Words in reg. 18(7) substituted (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(c) (with regs. 22-24)
F8Reg. 18(8) substituted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 7(8)(d) (with regs. 22-24)
Modifications etc. (not altering text)
C1Reg. 18 modified (4.7.2023) by The Building Safety (Responsible Actors Scheme and Prohibitions) Regulations 2023 (S.I. 2023/753), regs. 1(1), 37(3)
18.—(1) This regulation applies where it appears to a local authority that unauthorised building work has been carried out on or after 11th November 1985.
(2) Where this regulation applies, the owner (in this regulation referred to as “the applicant”) may apply in writing to the local authority for a regularisation certificate in accordance with this regulation, and shall send with the application—
(a)a statement that the application is made in accordance with this regulation,
(b)a description of the unauthorised work,
(c)so far as is reasonably practicable, a plan of the unauthorised work, and
(d)so far as is reasonably practicable, a plan showing any additional work required to be carried out to secure that the unauthorised work complies with the requirements relating to building work in the building regulations which were applicable to that work when it was carried out (in this regulation referred to as “the relevant requirements”).
(3) Where a local authority receive an application in accordance with this regulation, they may require the applicant to take such reasonable steps, including laying open the unauthorised work for inspection by the authority, making tests and taking samples, as the authority think appropriate to ascertain what work, if any, is required to secure that the relevant requirements are met.
(4) When the applicant has taken any such steps required by the local authority as are described in paragraph (3), and having had regard to any direction given in accordance with sections 8 and 9 of, and Schedule 2 to, the Act dispensing with or relaxing a requirement in building regulations which applies to the unauthorised work, the local authority shall notify the applicant—
(a)of the work which in their opinion is required to comply with the relevant requirements or those requirements as dispensed with or relaxed, or
(b)that they cannot determine what work is required to comply with the relevant requirements or those requirements as dispensed with or relaxed, or
(c)that no work is required to secure compliance with the relevant requirements or those requirements as dispensed with or relaxed.
(5) Where the local authority have been able to satisfy themselves, after taking all reasonable steps for that purpose that—
(a)the relevant requirements have been satisfied (taking account of any work carried out and any dispensation or relaxation given in accordance with sections 8 and 9 of, and Schedule 2 to, the Act), or
(b)no work is required to secure that the unauthorised work satisfies the relevant requirements (taking account of any such dispensation or relaxation),
they may give a certificate to that effect (in this regulation referred to as “a regularisation certificate”).
(6) A regularisation certificate shall be evidence (but not conclusive evidence) that the relevant requirements specified in the certificate have been complied with.
(7) Where this regulation applies, regulations 12 and 14 shall not apply, and neither the supply of plans nor the taking of any other action in accordance with this regulation is to be treated for the purposes of section 16 of the Act as the deposit of plans in accordance with building regulations.
(8) In this regulation, “unauthorised building work” means building work other than work in relation to which an initial notice, an amendment notice or a public body's notice has effect, which is done without—
(a)a building notice being given to the local authority;
(b)full plans of the work being deposited with the local authority; or
(c)a notice of commencement of work being given, in accordance with regulation 16(1), where a building notice has been given or full plans have been deposited.
Extent Information
E2This version of this provision applies to Wales only; a separate version has been created for England only
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: