Search Legislation

The Building Regulations 2010

 Help about what version

What Version

 Help about advanced features

Advanced Features

Status:

There are multiple versions of this provision on screen. These apply to different geographical extents. Help about Status

Close

Status

The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents. Insertions and repeals of text do not give rise to such multiple versions.

Changes to legislation:

The Building Regulations 2010, Section 16 is up to date with all changes known to be in force on or before 14 November 2026. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Regulation 16:

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

[F1Notices in relation to building work]E

This section has no associated Explanatory Memorandum

16.—(1) Subject to paragraphs (8) and (9), a person who proposes to carry out building work shall not [F2start that work] unless—

(a)that person has given the [F3relevant authority] notice of intention to [F4start work]; and

(b)at least two days have elapsed since the end of the day on which the notice was given.

[F5(2) Subject to paragraph (8), a person carrying out building work must notify the [F6relevant authority] as required by the authority in accordance with paragraph (3).

(3) Subject to the conditions in paragraphs (3A) and (3B), where a [F7relevant authority] receives notice of intention to [F8start work] under paragraph (1) they may give the person carrying out the work a notice in writing which—

(a)requires that person to notify the authority that a specified stage of the work (other than a stage specified in paragraphs (4) and (5)) has been reached; and

(b)may specify one or more periods of time, applying to each such required notification, which may be either or both of the following—

(i)a period before or after the work has been carried out within which the notification must be made; and

(ii)a period during which the work concerned must not be covered up.

(3A) A [F9relevant authority] may only specify a stage of the building work in accordance with paragraph (3)(a) if at the time they do so they intend to carry out an inspection of that stage.

(3B) For the purposes of paragraph (3A) the [F10relevant authority]'s intention to carry out an inspection of a stage of building work must be based on their assessment of the risk of breach of these Regulations if they do not inspect the work.]

[F11(3C) Not more than five days after the day on which work is to be regarded as commenced the person carrying out the work must give a notice to that effect to the relevant authority.

[F12(3CA) Subject to paragraphs (3CB) and (3CC), where building work, to which an application for building control approval with full plans relates, relates to the provision of one or more dwellings, or one or more bedspaces in purpose-built student accommodation, and the building which consists of or contains the dwellings or bedspaces is a residential building (as defined in regulation 7 of the BSL Regulations), a notice under paragraph (3C) must also—

(a)if the levy charging conditions are met [F13, but subject to sub-paragraph (c)]—

(i)include a statement setting out the number of dwellings, if any, to be provided as a result of the building work to which the application for building control approval with full plans relates which are within any of sub-paragraphs (a) to (c) of regulation 8(1) of the BSL Regulations;

(ii)include a statement setting out the levy charging information, in accordance with regulation 16A (levy charging information), in relation to the application for building control approval with full plans to which the notice relates;

(iii)include a statement setting out the applicable planning information;

(iv)be accompanied by evidence as to the matters described in paragraphs (i), (ii) and (iii),

(b)if the levy charging conditions are not met [F14, but subject to sub-paragraph (c)]—

(i)include a statement setting out the applicable planning information;

(ii)include a statement explaining how the levy charging conditions are not met;

(iii)be accompanied by evidence as to the matters described in paragraphs (i) and (ii), F15...

(c)[F16if a statement or evidence required under sub-paragraph (a) or (b)] has been given previously in relation to the building work to which the application for building control approval with full plans relates, include a statement to that effect [F17instead of the statement or evidence] .

(3CB) Where the application for building control approval with full plans referred to in paragraph (3CA) is an application relating to building work in respect of which the regulator is the building control authority under section 91ZB(2) of the 1984 Act—

(a)the evidence required to accompany a notice under paragraph (3C) must instead be sent to the collecting authority together with a statement identifying the application to which the evidence relates;

(b)the documents referred to in sub-paragraph (a) must be sent to the collecting authority, by the client, on the same day that the notice under paragraph (3C) is sent to the regulator.

(3CC) Where, in relation to the application for building control approval with full plans referred to in paragraph (3CA), no statement under regulation 14ZA(1)(c) to (f) has previously been required, the notice under paragraph (3C) must include whichever of those statements under regulation 14ZA(1)(c) to (f) that is applicable.]

(3D) The relevant authority may take such steps, including—

(a)requiring information;

(b)laying open of work for inspection,

as the authority thinks appropriate to check whether the work is to be regarded as commenced.

(3E) If the relevant authority are not satisfied the work is to be regarded as commenced they must give the person carrying out the work a notice to that effect (“rejection notice”) within four weeks of the date the notice under paragraph (3C) is given, and the rejection notice must give the reasons for rejection.

(3F) Where a notice is given under paragraph (3C) and the period referred to in paragraph (3E) expires without a rejection notice being given, then the work is to be regarded as commenced.

(3G) If the person carrying out the work accepts the rejection notice they may not give a further notice under paragraph (3C) unless, having regard to the reasons given by the relevant authority, they are satisfied the work is to be regarded as commenced.

(3H) A person who gave the notice under paragraph (3C) may appeal to the First-tier Tribunal against the decision of the relevant authority to reject the notice provided the appeal is made within 21 relevant days beginning with the day after the day on which the relevant authority gives the rejection notice.

(3I) The First-tier Tribunal may allow an appeal under paragraph (3H) only if it is satisfied that the decision appealed against was wrong on one or more of the following grounds—

(a)that the decision was based on an error of fact;

(b)that the decision was wrong in law;

(c)that the decision was unreasonable; or

(d)that the decision was made without following the procedures set out in the Act or regulations made under that Act.

(3J) For the purposes of paragraphs (3C) to (3I) the provisions of regulation 46A (lapse of building control approval: commencement of work) apply to determine whether work is to be regarded as commenced.]

(4) Subject to paragraph (8), a person carrying out building work shall, not more than five days after that work has been completed, give the [F18relevant authority] [F19a notice which complies with paragraph (4A)].

[F20(4A) The notice under paragraph (4) must include—

(a)the name, address, telephone number and (if available) email address of the client;

(b)the name, address, telephone number and (if available) email address of the principal contractor (or sole contractor) and the principal designer (or sole or lead designer);

(c)a statement that the building work is complete;

(d)a statement, signed by the client, confirming that to the best of the client’s knowledge the work complies with all applicable requirements of the building regulations;

(e)[F21subject to paragraph (4B),] a statement given by each principal contractor (or sole contractor) for the work and each principal designer (or sole or lead designer) for the work, signed by the person to which the declaration relates, which includes—

(i)the name, address, telephone number and (if available) email address of that person;

(ii)the dates of their appointment, and

(iii)confirmation—

(aa)in the case of a principal contractor (or sole contractor), that they fulfilled their duties as a principal contractor under Part 2A (dutyholders and competence) of these Regulations;

(bb)in the case of a principal designer (or sole or lead designer), that they fulfilled their duties as a principal designer under Part 2A (dutyholders and competence) of these Regulations [F22;

(f)if, under regulation 14(1)(g) or (h), building safety levy information was required to be provided with the application for building control approval with full plans in relation to the building work or an updated application in relation to that application, a levy liability statement under paragraph (5B).]]

[F23(4B) If for any reason a person carrying out building work is unable to include a statement for a person mentioned under paragraph (4A)(e), the person carrying out the building work must include a statement giving the reasons why that person’s statement has not been included.]

(5) Where a building is being erected [F24to which the Regulatory Reform (Fire Safety) Order 2005 M1 applies, or will apply after the completion of the work ], and that building (or any part of it) is to be occupied before completion, the person carrying out that work shall give the [F25relevant authority] [F26a notice which complies with paragraph (5A) at least 5 days] before the building or any part of it is occupied.

[F27(5A) The notice under paragraph (5) must include—

(a)the name, address, telephone number and (if available) email address of the client;

(b)the name, address, telephone number and (if available) email address of the principal contractor (or sole contractor) and the principal designer (or sole or lead designer);

(c)the date when the building or any part of it is to be occupied;

(d)a statement, signed by the client, confirming that to the best of the client’s knowledge, regardless of the completion of the current building work, regulation 38 and Part B of Schedule 1 are currently complied with in relation to those parts of the building which are to be occupied before completion of the work;

(e)[F28subject to sub-paragraph (f),] a statement given by each principal contractor (or sole contractor) for the work and each principal designer (or sole or lead designer) for the work, signed by the person to which the declaration relates, which includes—

(i)the name, address, telephone number and (if available) email address of that person;

(ii)the dates of their appointment, and

(iii)confirmation—

(aa)in the case of a principal contractor (or sole contractor), that they fulfilled their duties as a principal contractor under Part 2A (dutyholders and competence) of these Regulations;

(bb)in the case of a principal designer (or sole or lead designer), that they fulfilled their duties as a principal designer under Part 2A (dutyholders and competence) of these Regulations [F29;]]

[F30(f)if a person carrying out building work is unable to include a statement for a person mentioned in sub-paragraph (e), the person carrying out the building work must include a statement giving reasons why that person’s statement has not been included.]

[F31(5B) The “levy liability statement” is a statement, signed by the named client, that—

(a)a notice of no charge has been received in relation to the application referred to in paragraph (4A)(f), or an updated application relating to it, and has not been cancelled under regulation 43 or 53 of the BSL Regulations, or

(b)the levy liability amount in relation to the application referred to in paragraph (4A)(f), or the updated application relating to it, has been paid in full,

and for these purposes, “notice of no charge” and “levy liability amount” have the same meaning as in the BSL Regulations.]

(6) A person who fails to comply with paragraphs (1) [F32or (2)] shall comply within a reasonable time with any notice given by the [F33relevant authority] requiring that person to cut into, lay open or pull down so much of the work as prevents them from ascertaining whether these Regulations have been complied with.

(7) If the [F34relevant authority] have given notice specifying the manner in which any work contravenes the requirements in these Regulations, a person who has carried out any further work to secure compliance with these Regulations shall within a reasonable time after the completion of such further work give notice to the [F34relevant authority] of its completion.

(8) Paragraphs (1) to (4) apply only to a person who is required by regulation 12 to give a building notice or [F35an application for building control approval with full plans].

(9) Paragraph (1) does not apply where regulation 12(8) applies.

[F36(10) In this regulation—

(a)the “levy charging conditions” are—

(i)the building work to which the application for building control approval with full plans relates would result in a new building which includes residential floorspace, an existing building which includes residential floorspace where previously it had none (whether by extension or change of use), or an existing building with an increased total area of residential floorspace (whether by extension or change of use),

(ii)the building work to which the application relates is, or is anticipated to be, major residential development or is part of a wider development which is, or is anticipated to be, major residential development, and

(iii)the named client or, if there is more than one named client, each of them, in relation to the application is not an exempt person;

(b)subject to sub-paragraph (c), “applicable planning information” is—

(i)where a statement under regulation 14ZA(1)(a) stated that planning permission is not required, a statement confirming whether or not that remains the case and if it has changed setting out details of the change;

(ii)where a statement under regulation 14ZA(1)(a) stated that section 33 of the Planning Act 2008 applies, a statement confirming whether or not that remains the case and also identifying the development consent under section 31 of the Planning Act 2008 and if it has changed setting out details of the change;

(iii)where regulation 14ZA(1)(b)(i) or (iv) applied to the application for building control approval with full plans at the time that application was made, a statement confirming that information identifying the planning permission or prior approval have already been provided but if the planning permission has changed since the time that application was made the statement must set out details of the planning permission as updated;

(iv)where regulation 14ZA(1)(b)(ii) or (iii) applied to the application for building control approval with full plans at the time that application was made, information identifying the planning permission granted;

(v)where regulation 14ZA(1)(b)(v) or (vi) applied to the application for building control approval with full plans at the time that application was made, information identifying the prior approval and how the prior approval requirement is satisfied,

but where the planning permission expressly provides for the development to be carried out in phases the reference in paragraph (iii) and (iv) to the planning permission is a reference to the planning permission for the particular phase or phases of the development to which the application for building control approval with full plans relates;

(c)if, at the date the applicable planning information is to be included in a notice or application, no statement has previously been required under regulation 14ZA(1)(a) or (b), then the “applicable planning information” is whichever of those statements under regulation 14ZA(1)(a) or (b) that is applicable, as updated;

(d)for the purposes of sub-paragraph (b)(v), a prior approval requirement is satisfied, in relation to a development, if the outcome of the prior approval application is that—

(i)prior approval is given (or is deemed to be given), or

(ii)the local planning authority has determined prior approval is not required (where local planning authority has the meaning given in section 336 of TCPA 1990).]

[F37(11) In paragraph (3CA), the references to dwellings do not include references to purpose-built student accommodation.]

Extent Information

E1This version of this provision applies to England only; a separate version has been created for Wales only

Textual Amendments

F5Reg. 16(2)-(3B) substituted for reg. 16(2)(3) (E., but only in relation to excepted energy buildings in W.) (6.4.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 9(a), Sch. 1 (with regs. 1(3), 45-47) (as amended by S.I. 2013/181, reg. 5, Sch.)

F22Reg. 16(4A)(f) inserted and semicolon substituted for full stop at the end of reg. 16(4A)(e) (E.) (1.10.2026) by The Building Safety Levy (England) Regulations 2025 (S.I. 2025/1236), regs. 1(2), 57(2) (with reg. 1(5)(6))

F24Words in reg. 16(5) added (E., but only in relation to excepted energy buildings in W.) (6.4.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 9(b), Sch. 1 (with regs. 1(3), 45-47) (as amended by S.I. 2013/181, reg. 5, Sch.)

F29Reg. 16(5A)(e): semicolon substituted for full stop (E.) (7.10.2025) by The Building Regulations etc. (Amendment) (England) Regulations 2025 (S.I. 2025/1017), regs. 1(2), 9(d) (with reg. 11(3)(4))

F32Words in reg. 16(6) substituted (E., but only in relation to excepted energy buildings in W.) (6.4.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 9(c), Sch. 1 (with regs. 1(3), 45-47) (as amended by S.I. 2013/181, reg. 5, Sch.)

Marginal Citations

M1 S.I 2005/1541.

[F38Notices in relation to building work]W

16.—(1) Subject to paragraphs (8) and (9), a person who proposes to carry out building work shall not [F39start that work] unless—

(a)that person has given the [F40building control authority] notice of intention to [F41start work]; and

(b)at least two days have elapsed since the end of the day on which the notice was given.

[F42(2) Subject to paragraph (8), a person carrying out building work shall not—

(a)cover up any excavation for a foundation, any foundation, any damp-proof course or any concrete or other material laid over a site; or

(b)cover up in any way any drain or sewer to which these Regulations apply, unless that person has given the [F43building control authority] notice of intention to [F44start that work], and at least one day has elapsed since the end of the day on which the notice was given.

[F45(2A) Not more than 5 days after the day on which work is to be regarded as commenced the person carrying out the work must give a notice to that effect to the building control authority.

(2B) The building control authority may take such steps, including—

(a)requiring information;

(b)laying open of work for inspection,

as the authority thinks appropriate to check whether the work is to be regarded as commenced.

(2C) If the building control authority are not satisfied the work is to be regarded as commenced they must give the person carrying out the work a notice to that effect (“rejection notice”) within 4 weeks of the date the notice under paragraph (2A) is given, and the rejection notice must give the reasons for rejection and indicate what work needs to be completed for the work to be accepted as commenced.

(2D) Where a notice is given under paragraph (2A) and the period referred to in [F46paragraph (2C)] expires without a rejection notice being given, then the work is to be regarded as commenced.

(2E) If the person carrying out the work accepts the rejection notice they may not give a further notice under paragraph (2A) unless, having regard to the reasons given by the building control authority, they are satisfied the work is to be regarded as commenced.

(2F) A person who gave the notice under paragraph (2A) may appeal to the magistrates’ court against the decision of the building control authority to reject the notice provided the appeal is made within 15 F47... days beginning with the day after the day on which the building control authority gives the rejection notice.

(2G) The magistrates’ court may allow an appeal under paragraph (2F) only if it is satisfied that the decision appealed against was wrong on one or more of the following grounds—

(a)that the decision was based on an error of fact;

(b)that the decision was wrong in law;

(c)that the decision was unreasonable;

(d)that the decision was made without following the procedures set out in the Act or regulations made under that Act.

(2H) For the purposes of paragraphs (2A) to (2G), regulation 46B (lapse of building control approval: commencement of work: Wales) applies to determine whether work is to be regarded as commenced.]

(3) Subject to paragraph (8), a person who has laid, haunched or covered any drain or sewer in respect of which Part H of Schedule 1 (drainage and waste disposal) imposes a requirement shall give notice to that effect to the [F48building control authority] not more than five days after the completion of the work.]

F49(3A) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F49(3B) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(4) Subject to paragraph (8), a person carrying out building work shall, not more than five days after that work has been completed, give the [F50building control authority] notice to that effect.

[F51(4A) The notice under paragraph (4) must include—

(a)the name, address, telephone number and (if available) email address of the client;

(b)the name, address, telephone number and (if available) email address of the principal contractor (or sole contractor) and the principal designer (or sole or lead designer);

(c)a statement that the building work is complete;

(d)a statement, signed by the client or an applicant acting on the client’s behalf, confirming that to the best of the client’s knowledge the work complies with all applicable requirements of the building regulations. Where a person has signed on the client’s behalf, a declaration from the client that they approve of this notice;

(e)a statement given by each principal contractor (or sole contractor) for the work and each principal designer (or sole or lead designer) for the work, signed by the person to which the declaration relates, which includes—

(i)the name, address, telephone number and (if available) email address of that person,

(ii)the dates of their appointment, and

(iii)confirmation—

(aa)in the case of a principal contractor (or sole contractor), that they fulfilled their duties as a principal contractor under Part 2B (dutyholders and competence) of these Regulations;

(bb)in the case of a principal designer (or sole or lead designer), that they fulfilled their duties as a principal designer under Part 2B (dutyholders and competence) of these Regulations.

(4B) If for any reason a person carrying out building work is unable to include a statement for a person mentioned under paragraph (4A)(e), the person carrying out the building work must include a statement giving the reasons why that person’s statement has not been included.]

(5) Where a building is being erected F52[F53to which the Regulatory Reform (Fire Safety) Order 2005 applies, or will apply after the completion of the work ], and that building (or any part of it) is to be occupied before completion, the person carrying out that work shall give the [F54building control authority] [F55a notice which complies with paragraph (5A) at least 5 F47... days] before the building or any part of it is occupied.

[F56(5A) The notice under paragraph (5) must include—

(a)the name, address, telephone number and (if available) email address of the client;

(b)the name, address, telephone number and (if available) email address of the principal contractor (or sole contractor) and the principal designer (or sole or lead designer);

(c)the date when the building or any part of it is to be occupied;

(d)a statement, signed by the client or an applicant acting on the client’s behalf, confirming that to the best of the client’s knowledge, regardless of the completion of the current building work, regulation 38 and Part B of Schedule 1 are currently complied with in relation to those parts of the building which are to be occupied before completion of the work. Where a person has signed on the client’s behalf, a declaration from the client that they approve of this notice;

(e)a statement given by each principal contractor (or sole contractor) for the work and each principal designer (or sole or lead designer) for the work, signed by the person to which the declaration relates, which includes—

(i)the name, address, telephone number and (if available) email address of that person,

(ii)the dates of their appointment, and

(iii)confirmation—

(aa)in the case of a principal contractor (or sole contractor), that they fulfilled their duties as a principal contractor under Part 2B (dutyholders and competence) of these Regulations;

(bb)in the case of a principal designer (or sole or lead designer), that they fulfilled their duties as a principal designer under Part 2B (dutyholders and competence) of these Regulations.

(5B) If a person carrying out building work is unable to include a statement for a person mentioned in paragraph (5A)(e), the person carrying out the building work must include a statement giving reasons why that person’s statement has not been included.]

(6) A person who fails to comply with paragraphs (1) [F57to (3)] shall comply within a reasonable time with any notice given by the [F58building control authority] requiring that person to cut into, lay open or pull down so much of the work as prevents them from ascertaining whether these Regulations have been complied with.

(7) If the [F59building control authority] have given notice specifying the manner in which any work contravenes the requirements in these Regulations, a person who has carried out any further work to secure compliance with these Regulations shall within a reasonable time after the completion of such further work give notice to the [F59building control authority] of its completion.

(8) Paragraphs (1) to (4) apply only to a person who is required by regulation 12 to give a building notice or [F60an application for building control approval with full plans].

(9) Paragraph (1) does not apply where regulation 12(8) applies.

Extent Information

E2This version of this provision applies to Wales only; a separate version has been created for England only

Textual Amendments

F42Reg. 16(2)(3) substituted (W. in relation to excepted energy buildings to match the form in which those sub-provisions apply in relation to W. otherwise) (8.6.2018) by The Building Regulations &c. (Amendment) (Excepted Energy Buildings) (Wales) Regulations 2018 (S.I. 2018/558), regs. 1(2), 5(4)(a) (with reg. 29)

F49 Reg. 16(3A) (3B) omitted (W. in relation to excepted energy buildings to match the form in which those sub-provisions apply in relation to W. otherwise) (8.6.2018) by virtue of The Building Regulations &c. (Amendment) (Excepted Energy Buildings) (Wales) Regulations 2018 (S.I. 2018/558), regs. 1(2), 5(4)(b) (with reg. 29)

F52Words in reg. 16(5) added (W. for remaining purposes) (19.4.2013) by The Building Regulations &c. (Amendment) (Wales) Regulations 2013 (S.I. 2013/747), regs. 1(4), 7 (with regs. 1(2)(3), 35, 36)

F53Words in reg. 16(5) added (E., but only in relation to excepted energy buildings in W.) (6.4.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 9(b), Sch. 1 (with regs. 1(3), 45-47) (as amended by S.I. 2013/181, reg. 5, Sch.)

F57Words in reg. 16(6) substituted (W. in relation to excepted energy buildings to match the form in which the text applies in relation to W. otherwise) (8.6.2018) by The Building Regulations &c. (Amendment) (Excepted Energy Buildings) (Wales) Regulations 2018 (S.I. 2018/558), regs. 1(2), 5(4)(c) (with reg. 29)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources