Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 4E+WSupervision of Building Work Otherwise than by Local Authorities

Supervision of building work otherwise than by local authoritiesE+W

19.—(1) Regulations 12 (giving of a building notice or deposit of plans), 16 (notice of commencement and completion of certain stages of work), 17 (completion certificates), F1[F217A (Certificate for building occupied before work is completed)] 20 (provisions applicable to self-certification schemes), 27 (CO2 emission rate calculations), [F327A (fabric energy efficiency rate calculations), 27C (target primary energy rate calculations for new buildings),] F4F5... 37 (wholesome water consumption calculation), 41 (sound insulation testing), 42 (mechanical ventilation air flow rate testing), 43 (pressure testing), 44 (commissioning) [F6, 45 (testing of building work) and 46 (sampling of material)] shall not apply in respect of any work specified in an initial notice, an amendment notice or a public body's notice, which is in force.

[F7(2) Regulations 45 and 46 shall not apply in respect of any work in relation to which a final certificate or a public body's final certificate has been accepted by the local authority.]

Textual Amendments

F1Words in reg. 19(1) inserted (W. for remaining purposes) (19.4.2013) by The Building Regulations &c. (Amendment) (Wales) Regulations 2013 (S.I. 2013/747), regs. 1(4), 10 (with reg. 1(2)(3))

F2Words in reg. 19(1) inserted (E., but only in relation to excepted energy buildings in W.) (9.1.2013) by The Building Regulations &c. (Amendment) Regulations 2012 (S.I. 2012/3119), reg. 12, Sch. 1 (with regs. 1(3), 45-47)

F4Words in reg. 19(1) omitted (W. for remaining purposes) (17.6.2016) by virtue of The Building Regulations &c. (Amendment) (Wales) Regulations 2016 (S.I. 2016/611), regs. 1(4), 2(6) (with reg. 1(3))

F5Words in reg. 19(1) omitted (E., but only in relation to excepted energy buildings in W.) (6.4.2016) by virtue of The Building Regulations &c. (Amendment) Regulations 2016 (S.I. 2016/285), regs. 1(4), 2(6) (with reg. 1(3))

[F8Regulator’s notices: description of work and connectionE+W

19A.  For the purposes of section 91ZB(1) of the Act, a regulator’s notice may be given in relation to any building work (which is not higher-risk building work) where—

(a)the client for the building work is proposing to undertake higher-risk building work on the same site;

(b)the regulator’s notice includes all the building work to be carried out on the site which is not higher-risk building work; and

(c)the client has appointed the same principal contractor for the building work and the higher-risk building work.

Regulator’s notices: content of noticesE+W

19B.  A regulator’s notice must be in writing and must include—

(a)the name, address, telephone number and (if available) email address of the client for the project to which the notice relates;

(b)a statement that the notice is a regulator’s notice under section 91ZB of the Act;

(c)the location of the proposed building work to which the regulator’s notice is to apply;

(d)a description of the proposed building work to which the regulator’s notice is to apply, including a statement explaining how that work is connected to higher-risk work and the location on the site of that higher-risk building work;

(e)a statement giving the date it is proposed the building work will start and how long it is proposed to take to complete;

(f)a plan to a scale of not less than 1:1250 showing—

(i)the size and position of the building, or the building as extended, and its relationship to adjoining boundaries;

(ii)the boundaries of the curtilage of the building, or the building as extended, and the size, position and use of every other building or proposed building within that curtilage;

(iii)the width and position of any street on or within the boundaries of the curtilage of the building or the building as extended;

(g)a declaration, signed by the client and signed by an employee of the regulator who is authorised to do so, confirming—

(i)the client and the regulator consent to the giving of the notice;

(ii)the proposed building work to which the notice relates includes no higher-risk building work;

(iii)the proposed building work falls within the requirements of regulation 19A (regulator’s notices: description of work and connection);

(iv)they understand the proposed building work is to be subject to the procedural requirements of these Regulations.

Regulator’s notices: grounds for rejectionE+W

19C.(1) The following grounds are prescribed for the purposes of section 91ZC(2) of the Act—

(a)the conditions in regulation 19A (regulator’s notices: description of work and connection) are not satisfied in relation to the work specified in the notice;

(b)the work specified in the notice is not within the area of the local authority;

(c)that an application for building control approval, an initial notice or a public body’s notice has been given in relation to the work (or any part of it);

(d)the notice does not comply with the requirements of regulation 19B (regulator’s notices: content of notices).

(2) For the purposes of section 91ZC(3) of the Act a notice of rejection must be given within five days of the day on which the regulator’s notice is given.

Regulator’s notices: appealsE+W

19D.(1) An appeal to the First-tier Tribunal under section 91ZC(4) of the Act must be made within 21 relevant days beginning with the day after the day on which the local authority notifies the person under section 91ZC(3) of the Act.

(2) The First-tier Tribunal may allow an appeal under section 91ZC(4) of the Act only if it is satisfied that the decision appealed against was wrong on one or more of the following grounds—

(a)that the decision was based on an error of fact;

(b)that the decision was wrong in law;

(c)that the decision was unreasonable; or

(d)that the decision was made without following the procedures set out in the Act or regulations made under that Act.

(3) If the First-tier Tribunal allows an appeal it may quash or vary the decision.

(4) The power of the First-tier Tribunal to award costs does not apply in relation to an appeal under this regulation.

Regulator’s notices: directionE+W

19E.(1) In relation to work which is the subject of a regulator’s notice, the regulator may make a direction as to the way in which any of the following documents are given (which may include specifying cases where they must be given electronically via a website address provided for that purpose by the regulator)—

(a)a building notice under regulation 13 (particulars and plans where a building notice is given);

(b)an application under regulation 14 (applications for building control approval with full plans);

(c)any notice under regulation 16 (notices in relation to building work);

(d)an application under regulation 18 (unauthorised building work);

(e)any documents that are required to accompany any notice or application referred to in sub-paragraph (a) to (d);

(f)a notice under regulation 25A(2), 27(2) or (3), 27A(2) or (3), 27C(2) or (3), 37(1), 38(2B) or (2G), 41(4), 42(2), 43(2), 44(3) and 44ZA(2);

(g)a copy of results under regulation 41(2).

(2) A direction must specify the date on which it comes into effect, which must not be earlier than seven days after it is published.

(3) Where the regulator has made and published a direction in accordance with this regulation, an application (or any document that accompanied the application) of the type mentioned in the direction must, from the date specified in the direction, be given in accordance with the direction.

(4) The regulator may, by a further direction, amend or revoke a direction made under this regulation.

Regulator’s notices: local land chargesE+W

19F.  The functions of local authorities under the Local Land Charges Act 1975, as they relate to building work for which the regulator is the building control authority by reason of a regulator’s notice under section 91ZB of the Building Act 1984, are prescribed for the purposes of paragraph (b) of the definition of “relevant function” in paragraph 2(5) of Schedule 3 to the Building Safety Act 2022.]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources