The Infrastructure Planning (Compulsory Acquisition) Regulations 2010

Notice of proposed provision

This section has no associated Explanatory Memorandum

7.—(1) The applicant must give notice of the proposed provision to—

(a)each authority which, in relation to the proposed provision, is a relevant local authority within the meaning given by section 102(5);

(b)the Greater London Authority if the land to which the proposed provision relates, or any part of it, is in Greater London;

(c)each person who is within one or more of the categories set out in section 57; and

(d)each person listed in Column 1 of Schedule 2 in the circumstances described in Column 2 of that Schedule.

(2) The notice referred to in paragraph (1) must contain the following—

(a)the name and address of the applicant;

(b)a statement to the effect that an application for an order granting development consent has been made to the Commission, that the Commission has accepted the application, and the reference number applied to that application by the Commission;

(c)details of the application, or specified matters, to which the proposed provision relates;

(d)a description of the additional land;

(e)a map showing the location of the additional land;

(f)a statement of reasons as to why the additional land is required;

(g)a statement indicating how the order that contains the authorisation of the compulsory acquisition of the additional land is proposed to be funded;

(h)a statement that a copy of the proposed provision, the map, the revised draft order and any information submitted with the proposed provision are available for inspection free of charge at the places (including at least one address in the vicinity of the additional land) and the times set out in the notice;

(i)the latest date on which those documents will be available for inspection (being a date not earlier than the deadline under paragraph (l));

(j)a statement as to whether a charge will be made for copies of any of the documents and, if so, the amount of any charge;

(k)details of how representations (giving notice of the person’s interest in, or objection to, the proposed provision) can be made, a statement that such representations must be made on a registration form, and the address to which such representations may be sent; and

(l)the deadline for receipt of those representations by the Commission, which must not be earlier than the end of a period of at least 28 days beginning with the day after the day on which the person receives the notice.