32.—(1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme for the management of any accumulations [or] and deposits whose effects may be harmful or visible or otherwise noticeable from outside the Order limits has been submitted to and approved by the Commission.

(2) The approved scheme for the management of accumulations and deposits must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development.