Search Legislation

The London Gateway Port Harbour Empowerment Order 2008

Changes over time for: Cross Heading: The authorised works in combination with the related development

 Help about opening options

Alternative versions:

Status:

Point in time view as at 16/05/2008.

Changes to legislation:

There are currently no known outstanding effects for The London Gateway Port Harbour Empowerment Order 2008, Cross Heading: The authorised works in combination with the related development. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

The authorised works in combination with the related developmentE+W+S

3.  In circumstances where the related development is materially implemented and the authorised works are carried out, paragraphs 4 to 13 shall apply.E+W+S

Commencement Information

I1Sch. 6 para. 3 in force at 16.5.2008, see art. 1

4.  None of the B1(b), B1(c), B2 or B8 uses or the authorised works shall be first occupied or brought into beneficial use until the interim highway works have been practically completed.E+W+S

Commencement Information

I2Sch. 6 para. 4 in force at 16.5.2008, see art. 1

5.—(1) This paragraph shall apply unless the Highways Agency acting on behalf of the Secretary of State for Transport gives notice to the Harbour Authority that the final highway works need not be carried out.E+W+S

(2) Subject to sub-paragraph (1), no more than the total number of berths forming part of the authorised works set out in column (1) of the table and the corresponding total amount of B1(b), B1(c), B2 or B8 floorspace set out in column (2) of that table shall be brought into beneficial use or first occupied until the final highway works have been practically completed—

(1)

Number of berths

(2)

Maximum amount of permitted B1(b), B1(c), B2 or B8 floorspace

1 berth503,044m2 with the Ro-Ro (or 579,912m2 without the Ro-Ro)
2 berths456,812m2 with the Ro-Ro (or 533,680m2 without the Ro-Ro)
3 berths410,580m2 with the Ro-Ro (or 487,448m2 without the Ro-Ro)
4 berths364,348m2 with the Ro-Ro (or 441,216m2 without the Ro-Ro)
5 berths318, 116m2 with the Ro-Ro (or 394, 9842 without the Ro-Ro)
6 berths271,884m2 with the Ro-Ro (or 348,752m2 without the Ro-Ro)

Commencement Information

I3Sch. 6 para. 5 in force at 16.5.2008, see art. 1

6.  No more than the following combinations of B1(b), B1(c), B2 and B8 floorspace set out in column (1) of the table and the corresponding number of berths forming part of the authorised works set out in column (2) of that table shall be first occupied or brought into beneficial use prior to the completion of the new access road as a single carriageway road together with a cycleway, footway and alongside the carriageway the provision for appropriate emergency stacking space for lorries accessing the authorised works and including a Pegasus crossing where the access road crosses diverted Footpath 190—E+W+S

(1)

Floorspace

(2)

Number of berths

377,000 m2Either the Ro-Ro or 1 berth without the Ro-Ro
324,000 m2Either the Ro-Ro and 1 berth or 2 berths without the Ro-Ro
271,000 m2Either the Ro-Ro and 2 berths or 3 berths without the Ro-Ro

Commencement Information

I4Sch. 6 para. 6 in force at 16.5.2008, see art. 1

7.  No more than the following combinations of B1(b), B1(c), B2 and B8 floorspace set out in column (1) of the table and the corresponding number of berths forming part of the authorised works set out in column (2) of that table shall be first occupied or brought into beneficial use prior to the completion of the new access road as a dual carriageway road together with a cycleway and footway and including a Pegasus crossing where the access road crosses diverted Footpath 190—E+W+S

(1)

Floorspace

(2)

Number of berths

825,000 m2Either the Ro-Ro or 1 berth without the Ro-Ro
772,000 m2Either the Ro-Ro and 1 berth or 2 berths without the Ro-Ro
719,000 m2Either the Ro-Ro and 2 berths or 3 berths without the Ro-Ro
666,000 m2Either the Ro-Ro and 3 berths or 4 berths without the Ro-Ro
613,000 m2Either the Ro-Ro and 4 berths or 5 berths without the Ro-Ro
560,000 m2Either the Ro-Ro and 5 berths or 6 berths without the Ro-Ro
507,000 m2Either the Ro-Ro and 6 berths or 7 berths without the Ro-Ro

Commencement Information

I5Sch. 6 para. 7 in force at 16.5.2008, see art. 1

8.  No more than the following combinations of B1(b), B1(c), B2 and B8 floorspace set out in column (1) of the table and the corresponding number of berths forming part of the authorised works set out in column (2) of that table shall be first occupied or brought into beneficial use prior to the completion of highway works on the A13 at its junction with the A128 to provide an additional dedicated slip lane from the A13 eastbound off-slip to the A128 northbound together with associated flaring and signage—E+W+S

(1)

Floorspace

(2)

Number of berths

407,000m2Either the Ro-Ro or 1 berth without the Ro-Ro
390,000m2Either the Ro-Ro and 1 berth or 2 berths without the Ro-Ro
373,000m2Either the Ro-Ro and 2 berths or 3 berths without the Ro-Ro

Commencement Information

I6Sch. 6 para. 8 in force at 16.5.2008, see art. 1

9.  No more than 100,000m2 of the B1(b), B1(c), B2 and B8 development together with the Ro-Ro or, alternatively, 1 berth without the Ro-Ro, shall be first occupied or brought into beneficial use prior to the installation of a system for signalling traffic priority at the junction of the A13 with The Manorway.E+W+S

Commencement Information

I7Sch. 6 para. 9 in force at 16.5.2008, see art. 1

10.  No more than the following combinations of B1(b), B1(c), B2 and B8 floorspace set out in column (1) of the table and the corresponding number of berths forming part of the authorised works set out in column (2) of that table shall be first occupied or brought into beneficial use prior to the completion of the A13 / Manorway junction works—E+W+S

(1)

Floorspace

(2)

Number of berths

332,000m2Either the Ro-Ro or 1 berth without the Ro-Ro
315,000m2Either the Ro-Ro and 1 berth or 2 berths without the Ro-Ro
298,000m2Either the Ro-Ro and 2 berths or 3 berths without the Ro-Ro

Commencement Information

I8Sch. 6 para. 10 in force at 16.5.2008, see art. 1

11.  No more than 157,000m2 of B1(b), B1(c), B2 and B8 development shall be first occupied in combination with the bringing into beneficial use of the Ro-Ro or, alternatively, 1 berth without the Ro-Ro, prior to the completion of the following works—E+W+S

(a)The Sorrells/A1014 junction works;

(b)a Toucan Crossing on Springhouse Road at its junction with Manorway East;

(c)improvements as approved by the appropriate authority to the two pedestrian subways at The Manorway; and

(d)noise mitigation works for the new Sorrells roundabout as approved by the appropriate authority.

Commencement Information

I9Sch. 6 para. 11 in force at 16.5.2008, see art. 1

12.  No more than 167,000m2 of B1(b), B1(c), B2 and B8 development and the Ro-Ro or, alternatively, 1 berth without the Ro-Ro, shall be first occupied or brought into beneficial use prior to the completion of the construction of acoustic barriers where appropriate—E+W+S

(a)along either side of The Manorway from its junction with the A13 to the new Sorrells roundabout;

(b)along the northern section of the new access road;

(c)along either side of the A13 from where it meets Stanford Road immediately west of the junction of Stanford Road and Buckingham Hill Road north-eastwards to the point north of Caldwell Road; and

(d)along the south side of the A13 from a point north of Hemley Road to the junction with Saffron Gardens,

in each case as approved by the appropriate authority and in conformity with Highways Agency Standard HA 66/95 “Environmental Barriers Technical Requirements” (or any standard which may replace it).

Commencement Information

I10Sch. 6 para. 12 in force at 16.5.2008, see art. 1

13.  No more than the following combinations of B1(b), B1(c), B2 and B8 floorspace set out in column (1) of the table and the corresponding number of berths forming part of the authorised works set out in column (2) of that table shall be first occupied or brought into beneficial use prior to the completion of re-surfacing works to provide a low noise road surface (in accordance with a scheme to be submitted to and approved by the appropriate authority) to The Manorway between the A13 junction and up to and including the junction with The Sorrells—E+W+S

(1)

Floorspace

(2)

Number of berths

768,000m2Either the Ro-Ro and 4 berths or 5 berths without the Ro-Ro
384,000m2Either the Ro-Ro and 5 berths or 6 berths without the Ro-Ro

Commencement Information

I11Sch. 6 para. 13 in force at 16.5.2008, see art. 1

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources