Search Legislation

The London Gateway Port Harbour Empowerment Order 2008

Changes over time for: Cross Heading: Pre-conditions to commencing specified work

 Help about opening options

Alternative versions:

Status:

Point in time view as at 01/09/2020.

Changes to legislation:

There are currently no known outstanding effects for The London Gateway Port Harbour Empowerment Order 2008, Cross Heading: Pre-conditions to commencing specified work. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Pre-conditions to commencing specified workE+W+S

4.—(1) Before beginning to construct any specified work other than an excluded work, the Harbour Authority shall submit to the Agency plans of the specified work and such further particulars available to it as the Agency may reasonably require.E+W+S

(2) Any specified work other than an excluded work shall not be constructed except in accordance with such plans as may be approved in writing by the Agency, or settled in accordance with paragraph 13(1).

(3) Any approval of the Agency required under this paragraph—

(a)shall be deemed to have been given if it is neither given nor refused in writing and with a statement of the grounds for refusal within two months of the submission of plans for approval; and

(b)may be given subject to such reasonable requirements as the Agency may impose for—

(i)the protection of any drainage work;

(ii)the protection of the fishery;

(iii)the protection of water resources;

(iv)the prevention of flooding;

(v)the prevention of pollution; and

(vi)the discharge of its environmental and recreational statutory duties (so far as may be necessary).

(4) Without prejudice to the generality of sub-paragraphs (1), (2) and (3), the requirements which the Agency may impose under those sub-paragraphs include—

(a)conditions as to the time and the manner in which any other work or operation is to be carried out; or

(b)conditions requiring the Harbour Authority at its own expense to—

(i)construct such protective works (“the protective works”), whether temporary or permanent, during the construction of the specified works (including the provision of flood banks, walls or embankments and other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary to safeguard any drainage work against damage or to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased by reason of a specified work;

(ii)provide or maintain means of access for the Agency; or

(iii)provide, maintain and operate arrangements for dealing with any pollution incidents which may occur during and as a result of the construction of the specified works.

(5) The Harbour Authority shall indemnify the Agency in respect of all costs, charges and expenses which the Agency may reasonably incur or have to pay or which it may sustain—

(a)in the examination or approval of plans under this paragraph; or

(b)in the inspection of the construction of the specified works affecting a drainage work or any protective works required by the Agency under this Schedule.

(6) Subject to sub-paragraphs (1) and (2), any specified work other than an excluded work and all protective works, shall be constructed—

(a)within such period (if any) as the Agency may approve at the time of approval or, upon an application by the Harbour Authority, may approve afterwards;

(b)in accordance with the plans approved or deemed to have been approved or settled under this Schedule; and

(c)to the reasonable satisfaction of the Agency;

and the Agency shall be entitled by its officer to watch and inspect the construction of such works.

(7) The Harbour Authority shall give to the Agency not less than 14 days’ notice in writing of its intention to commence construction of any specified work other than an excluded work and notice in writing of its completion not later than 7 days after the date on which it is brought into use.

(8) If any part of a specified work other than an excluded work comprising a structure in, over or under a watercourse is constructed otherwise than in accordance with the requirements of this Schedule, the Agency may by notice in writing require the Harbour Authority at the Harbour Authority’s own expense to comply with the requirements of this Schedule or, if the Harbour Authority so elects and the Agency consents in writing to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent as the Agency reasonably requires.

(9) Subject to sub-paragraph (10), if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (8) is served on the Harbour Authority, it has failed to begin taking steps to comply with the requirements of the notice and thereafter complete them within such reasonable period as may be specified in such notice, the Agency may execute the works specified in the notice and any expenditure reasonably incurred by it in so doing shall be recoverable from the Harbour Authority.

(10) In the event of any dispute as to whether sub-paragraph (8) is properly applicable to any work in respect of which notice has been served under that sub-paragraph or as to the reasonableness of the requirements of such a notice, the Agency shall not, except in a case of emergency, exercise the powers conferred by sub-paragraph (9) until the dispute has been finally determined.

Commencement Information

I1Sch. 10 para. 4 in force at 16.5.2008, see art. 1

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources