The London Gateway Port Harbour Empowerment Order 2008

Power to deviateE+W+S

14.—(1) In constructing and maintaining the works authorised by article 10(1) and in exercising the powers conferred by article 13 (power to dredge), the Harbour Authority may, to the extent of the limits of deviation or, for works authorised by article 13 (power to dredge), to the extent of the limits of deviation for dredging, deviate laterally from the lines or situations of those works shown on the deposited plans.

(2) In constructing and maintaining the works authorised by article 10(1), the Harbour Authority may deviate vertically from the levels of those works shown on the deposited sections to any extent downwards and up to 5 metres upwards.

(3) In exercising the powers conferred by article 13 (power to dredge), the Harbour Authority may deviate vertically to any extent not exceeding one metre downwards.

(4) In constructing so much of the combined footpath and bridleway shown on Sheets Nos. 268 and 269 of the deposited plans as lies between points X and W, the Harbour Authority may deviate laterally from the line shown on the footpath plans by 5 metres in any direction.

(5) In constructing so much of the footpath shown on Sheet No. 272 of the deposited plans as lies parallel to, but 5 metres north of, the definitive alignment of public footpath (part) No.81 in Thurrock, the Harbour Authority may deviate laterally from the line shown on the footpath plans by 2 metres in any direction.

(6) In constructing so much of the bridleway shown on Sheet No. 270 of the deposited plans running from a point 188 metres west of the crossing of footpath 190 (part) of the Thameshaven Branch line in a generally south-westerly, south, south-westerly direction for 1,000 metres to a point 180 metres south of the end of Wharf Road, the Harbour Authority may deviate laterally from the line shown on the deposited plans by 2 metres in any direction.

Commencement Information

I1Art. 14 in force at 16.5.2008, see art. 1