xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 5Environmental permits

PART 1Grant, variation, transfer and surrender of environmental permits

Time limits for determination

15.—(1) If—

(a)the regulator has not determined an application within the relevant period; and

(b)the applicant serves a notice on the regulator which refers to this paragraph,

the application is deemed to have been refused on the day on which the notice is served.

(2) In sub-paragraph (1) “the relevant period” means a period, calculated in accordance with paragraph 16, of—

(a)in the case of an application to transfer an environmental permit in whole or in part, 2 months;

(b)in a case where paragraph 6 applies, 4 months; or

(c)in any other case, 3 months,

or in any case, a longer period than the period in paragraph (a), (b) or (c), if it is agreed by the regulator and the applicant.