38. Upon signifying his approval or disapproval of the plans the engineer may specify any protective works, whether temporary or permanent, which in his opinion should be carried out before the commencement of the construction of the designated works to safeguard the safe, economic and efficient construction, operation and maintenance of the ticket hall, ventilation shaft and running tunnels proposed to be constructed within the safeguarded land as part of the CrossRail Scheme and such protective works as may be reasonably necessary for those purposes shall be constructed by Network Rail with all reasonable dispatch, at its own expense and Network Rail shall not commence the construction of the specified works until the engineer is satisfied that any protective works so constructed have been completed to the reasonable satisfaction of the engineer.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: