Statutory Instruments
LOCAL GOVERNMENT
TRANSPORT
Made
22nd November 2005
Laid before Parliament
28th November 2005
Coming into force
5th January 2006
The Secretary of State for Transport, in exercise of the powers conferred by section 163 of the Greater London Authority Act 1999(1), hereby makes the following Order:
1. This Order may be cited as the Transport for London (High Barnet Substation) Order 2005 and shall come into force on 5th January 2006.
2. The Secretary of State hereby gives consent to Transport for London for the disposal of the freehold interest in the land described in the Schedule.
Signed by authority of the Secretary of State for Transport
Karen Buck
Parliamentary Under Secretary of State
Department for Transport
22nd November 2005
Article 2
All that land formerly occupied by the electricity substation at High Barnet, Ivere Drive, Barnet, London EN5 shown edged red on the attached plan marked `High Barnet Substation'.
(This note is not part of the Order)
Section 163 of the Greater London Authority Act 1999 prohibits Transport for London from disposing of any freehold interest in operational land without the consent of the Secretary of State. Under section 164 of that Act, Transport for London is required to ensure that none of its subsidiaries does anything which Transport for London has no power to do (including anything which Transport for London has no power to do because the consent of the Secretary of State has not been obtained).
The land at Ivere Drive, Barnet, London EN5, which is the subject of this Order has been operational land as defined in section 163(8) of the Greater London Authority Act 1999. It comprises of the area formerly occupied by an electricity substation used in connection with the provision of railway services. Section 163(3) provides that consent under section 163 is not required in respect of land which was formerly operational land if a period of at least five years has elapsed since the land was last operational land, but such a period has not yet elapsed in this case. Its disposal therefore requires the consent of the Secretary of State. The land is currently vested in London Underground Limited, a subsidiary of Transport for London, and the disposal of the land will be made by that company.
By this Order the Secretary of State for Transport gives consent to Transport for London for the disposal of the land which is the subject of the Order.
A full regulatory impact assessment has not been produced for this instrument because it has no impact on the costs of business.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: