xmlns:atom="http://www.w3.org/2005/Atom"
66. The undertaker shall—
(a)at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
(b)supply the engineer with all such information as he may reasonably require with regard to a specified work or the method of constructing it.
67. NRI shall at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by NRI under this Part of this Schedule during their construction and shall supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.