Power to construct works

4.—(1) The Company may construct and maintain the scheduled works.

(2) Subject to article 5 below, the scheduled works shall be constructed in the lines or situations shown on the deposited plans and in accordance with the levels shown on the deposited sections.

(3) Subject to paragraph (5) below, the Company may carry out and maintain such of the following works as may be necessary or expedient for the purposes of, in connection with or in consequence of, the construction of the scheduled works, namely—

(a)works to alter the position of apparatus, including mains, sewers, drains and cables;

(b)works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;

(c)landscaping and other works to mitigate any adverse effects of the construction, maintenance or operation of the scheduled works;

(d)works for the benefit or protection of premises affected by the scheduled works; and

(e)such other works of whatever nature, including emergency escape shafts and ventilation shafts, as may be necessary or expedient.

(4) The Company may on or in any part of the lands numbered on the deposited plans 56, 57, 58 and 59 make and maintain, in connection with the scheduled works, a railway station together with all such works as may be necessary or expedient for the purposes of, in connection with, or in consequence of, the construction of the station.

(5) Paragraph (3) above shall only authorise the carrying out or maintenance of works outside the limits of deviation if the works are carried out on land specified in columns (1) and (2) of Schedule 2 to this Order for the purpose specified in relation to that land in column (3) of that Schedule.