Compensation following suspension or supplementary suspension order6

1

Where an order is made under paragraph 5 (orders after suspension of winning and working of minerals) or paragraph 6 (supplementary suspension orders) of Schedule 8–

a

section 83 shall have effect subject to the modification described in paragraph (2); and

b

the amount to be paid by way of compensation shall be assessed in accordance with section 83 (as so modified) and section 87 and then abated by the deduction of the appropriate portion of the sum of £8,100.

2

The modification referred to in paragraph (1) is the substitution, for subsections (2) and (3) of section 83, of the following subsections:–

2

If, on a claim made to the planning authority within the time and in the manner prescribed by regulations under this Act, it is shown that a person with an interest in the land to which the order relates or in the minerals in, on or under it–

a

has incurred expenditure in carrying out work which is rendered abortive by the provisions of the order, or

b

has otherwise sustained loss or damage which is directly attributable to the provisions of the order,

that authority shall pay to that person compensation in respect of that expenditure, loss or damage.

3

For the purposes of this section, any expenditure incurred in the preparation of plans for the purposes of any work, or upon other similar matters preparatory to it, shall be taken to be included in the expenditure incurred in carrying out that work.

3A

For the purposes of this section, works carried out for the purpose of removing or alleviating any injury to amenity caused by the mining and working of minerals on the land to which a suspension order or supplementary suspension order relates shall, unless included in another claim for compensation, be treated as loss or damage directly attributable to the provisions of the order.

3B

In calculating, for the purposes of this section, the amount of any loss or damage attributable to a suspension order or supplementary suspension order, no account shall be taken of the value of–

a

any mineral which cannot be won or worked;

b

any mineral waste which cannot be deposited; or

c

any void which cannot be filled,

in consequence of that order.