The Town and Country Planning (General Permitted Development) Order 1995

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

Changes over time for: Cross Heading: Procedure for applications for prior approval under Part 3

 Help about opening options

Version Superseded: 15/04/2015

Status:

Point in time view as at 01/04/2015.

Changes to legislation:

There are currently no known outstanding effects for The Town and Country Planning (General Permitted Development) Order 1995, Cross Heading: Procedure for applications for prior approval under Part 3. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

[F1Procedure for applications for prior approval under Part 3E+W

N.(1) The following provisions apply where under this Part a developer is required to make an application to a local planning authority for a determination as to whether the prior approval of the authority will be required.E+W

(2) The application shall be accompanied by—

(a)a written description of the proposed development;

(b)a plan indicating the site and showing the proposed development;

(c)the developer’s contact address; and

(d)the developer’s email address if the developer is content to receive communications electronically;

[F2(e)where paragraph (4) requires the Environment Agency to be consulted, a site-specific flood risk assessment;]

together with any fee required to be paid.

[F3(2A) The local planning authority may refuse an application where, in the opinion of the authority—

(a)the proposed development does not comply with, or

(b)the developer has provided insufficient information to enable the authority to establish whether the proposed development complies with,

any conditions, limitations or restrictions specified in this Part as being applicable to the development in question.

(2B) Paragraphs (3) to (6) and (8) shall not apply where a local planning authority refuses an application under paragraph (2A).]

(3) Where the application relates to prior approval as to transport and highways impacts of the development, on receipt of the application, where in the opinion of the local planning authority the development is likely to result in a material increase or a material change in the character of traffic in the vicinity of the site, the local planning authority shall consult—

[F4(a)where the increase or change relates to traffic entering or leaving a trunk road, the highway authority for the trunk road;]

(b)the local highway authority, where the increase or change relates to traffic entering or leaving a classified road or proposed highway, except where the local planning authority is the local highway authority; and

(c)the operator of the network which includes or consists of the railway in question, and the Secretary of State for Transport, where the increase or change relates to traffic using a level crossing over a railway.

(4) Where the application relates to prior approval as to the flooding risks on the site, on receipt of the application, the local planning authority shall consult the Environment Agency where the development is—

(a)in an area within Flood Zone 2 or Flood Zone 3; or

(b)in an area within Flood Zone 1 which has critical drainage problems and which has been notified to the local planning authority by the Environment Agency for the purpose of paragraph (ze)(ii) in the Table in Schedule 5 to the 2010 Order.

(5) The local planning authority shall notify the consultees referred to in paragraphs (3) and (4) specifying the date by which they must respond (being not less than 21 days from the date the notice is given).

(6) The local planning authority shall give notice of the proposed development—

(a)by site display in at least one place on or near the land to which the application relates for not less than 21 days of a notice which—

(i)describes the proposed development;

(ii)provides the address of the proposed development;

(iii)specifies the date by which representations are to be received by the local planning authority; or

(b)by serving a notice in that form on any adjoining owner or occupier.

[F5(7) The local planning authority may require the developer to submit such information regarding the impacts and risks referred to in paragraph J.2, K.2(b) or M.3(b), as the case may be, as the local planning authority may reasonably require in order to determine the application, which may include—

(a)assessments of impacts or risks;

(b)statements setting out how impacts or risks are to be mitigated.]

[F5(7) The local planning authority may require the developer to submit such information as the authority may reasonably require in order to determine the application, which may include—

(a)assessments of impacts or risks;

(b)statements setting out how impacts or risks are to be mitigated; or

(c)details of proposed operational development;]

(8) The local planning authority shall, when determining an application—

(a)take into account any representations made to them as a result of any consultation under paragraphs (3) or (4) and any notice given under paragraph (6);

(b)have regard to the National Planning Policy Framework issued by the Department for Communities and Local Government in March 2012 [F6, so far as relevant to the subject matter of the prior approval,] as if the application were a planning application; and

(c)in relation to the contamination risks on the site—

(i)determine whether, as a result of the proposed change of use, taking into account any proposed mitigation, the site will be contaminated land as described in Part 2A of the Environmental Protection Act 1990, and in doing so have regard to the Contaminated Land Statutory Guidance issued by Secretary of State for the Environment, Food and Rural Affairs in April 2012, and

(ii)if they determine that the site will be contaminated land, refuse to give prior approval.

(9) The development shall not be begun before the occurrence of one of the following—

(a)the receipt by the applicant from the local planning authority of a written notice of their determination that such prior approval is not required;

(b)the receipt by the applicant from the local planning authority of a written notice giving their prior approval; or

(c)the expiry of 56 days following the date on which the application was received by the local planning authority without the authority notifying the applicant as to whether prior approval is given or refused.

(10) The development shall be carried out—

(a)where prior approval is required, in accordance with the details approved by the local planning authority;

(b)where prior approval is not required, or where paragraph (9)(c) applies, in accordance with the details provided in the application referred to in paragraph (1),

unless the local planning authority and the developer agree otherwise in writing.

[F7(11) The local planning authority may grant prior approval unconditionally or subject to conditions reasonably related to the subject matter of the prior approval.]]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Schedule

The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Schedule as a PDF

The Whole Schedule you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.