SCHEDULE 2E+W

PART 20 E+WCOAL MINING DEVELOPMENT BY THE COAL AUTHORITYAND LICENSED OPERATORS

Class EE+W

Permitted developmentE+W

E.  The carrying out by the Coal Authority or a licensed operator, with the prior approval of the mineral planning authority, of development required for the maintenance or safety of a mine or a disused mine or for the purposes of ensuring the safety of the surface of the land at or adjacent to a mine or a disused mine.E+W

Prior approvalsE+W

E.1(1)  The prior approval of the mineral planning authority to development permitted by Class E is not required if—

(a)the external appearance of the mine or disused mine at or adjacent to which the development is to be carried out would not be materially affected;

(b)no building, plant or machinery, structure or erection—

(i)would exceed a height of 15 metres above ground level, or

(ii)where any building, plant, machinery, structure or erection is rearranged, replaced or repaired, would exceed a height of 15 metres above ground level or the height of what was rearranged, replaced or repaired, whichever is the greater,

and

(c)the development consists of the extension, alteration or replacement of an existing building, within the limits set out in paragraph (3).

(2) The approval referred to in Class E shall not be refused or granted subject to conditions unless the authority are satisfied that it is expedient to do so because—

(a)the proposed development would injure the amenity of the neighbourhood and modifications could reasonably be made or conditions reasonably imposed in order to avoid or reduce that injury, or

(b)the proposed development ought to be, and could reasonably be, sited elsewhere.

(3) The limits referred to in paragraph E.1(1)(c) are—

(a)that the cubic content of the building as extended, altered or replaced does not exceed that of the existing building by more than 25%, and

(b)that the floor space of the building as extended, altered or replaced does not exceed that of the existing building by more than 1,000 square metres.

Interpretation of Part 20E+W

F.1  For the purposes of Part 20—

F.2(1)  Subject to sub-paragraph (2), land is an authorised site for the purposes of Part 20 if—E+W

(a)it is identified in a grant of planning permission or any instrument by virtue of which planning permission is deemed to be granted as land which may be used for development described in this Part; or

(b)in any other case, it is land immediately adjoining an active access which, on 5th December 1988, was in use for the purposes of that mine in connection with coal-mining operations.

(2) For the purposes of sub-paragraph (1), land is not to be regarded as in use in connection with coal-mining operations if—

(a)it is used for the permanent deposit of waste derived from the winning and working of minerals; or

(b)there is on, over or under it a railway, conveyor, aerial ropeway, roadway, overhead power line or pipe-line which is not itself surrounded by other land used for those purposes.