F127Completion of works and reinstatement of road.

When the promoters have opened or broken up any portion of any road, they shall be under the following further obligations, namely,

1

They shall, with all convenient speed, and in all cases within four weeks at the most (unless the road authority otherwise consents in writing) complete the work on account of which they opened or broke up the same, and (subject to the formation, maintenance, or renewal of the tramway) fill in the ground and make good the surface, and, to the satisfaction of the road authority, restore the portion of the road to as good condition as that in which it was before it was opened or broken up, and clear away all surplus paving or metalling material or rubbish occasioned thereby:

2

They shall in the meantime cause the place where the road is opened or broken up to be fenced and watched, and to be properly lighted at night:

3

They shall bear or pay all reasonable expenses of the repair of the road for six months after the same is restored, as far as those expenses are increased by the opening or breaking up.

If the promoters aforesaid fail to comply in any respect with the provisions of the present section, they shall for every such offence (without prejudice to the enforcement of specific performance of the requirements of this Act or to any other remedy against them) be liable to a penalty not exceeding F2level 2 on the standard scale, and to a further penalty not exceeding five pounds for each day during which any such failure continues after the first day on which such penalty is incurred.