(1)Section 36D of the Electricity Act 1989 (proceedings for questioning certain decisions under section 36) is amended as set out in subsections (2) to (4).
(2)For subsection (3) substitute—
“(3)This section applies to a decision under any of the following—
(a)section 36 (application for consent for generating station);
(b)section 36C (application for variation of section 36 consent);
(c)section 37 (application for consent for overhead lines);
(d)section 37A (application for variation of section 37 consent);
(e)section 37B (variation of consents by Scottish Ministers);
(f)section 37C (consents and variation of consents in Scotland: correction of errors).”
(3)In subsection (4), for “taken” substitute “published by the Scottish Ministers”.
(4)In the heading, for “under section 36” substitute “of the Scottish Ministers”.
(5)In Schedule 8 to the Electricity Act 1989, in paragraph 5B (proceedings for questioning certain decisions under paragraph 3(2)), in sub-paragraph (4), for “taken” substitute “published by the Scottish Ministers”.
(6)In section 237 of the Town and Country Planning (Scotland) Act 1997 (challenges to validity of development plans and certain orders, decisions and directions), in subsection (3), after paragraph (b) insert—
“(ba)any decision to give a direction under section 57(2) or (2ZA);”.
(7)The amendments made by this section apply only in relation to decisions made on or after the date on which this section comes into force.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: