Search Legislation

Nuclear Energy (Financing) Act 2022

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Cross Heading: Licence modifications

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the Nuclear Energy (Financing) Act 2022, Cross Heading: Licence modifications. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Licence modificationsE+W+S

6Licence modifications: designated nuclear companiesE+W+S

(1)The Secretary of State may modify—

(a)a condition of a nuclear company’s electricity generation licence;

(b)a term of a nuclear company’s electricity generation licence.

(2)The Secretary of State may exercise the power under subsection (1) only for the purpose of facilitating investment in the design, construction, commissioning and operation of nuclear energy generation projects.

(3)The power under subsection (1) may be exercised in relation to a nuclear company only at a time when a designation under section 2(1) has effect in relation to the company.

(4)When exercising the power under subsection (1), the Secretary of State must have regard to—

(a)the duties of the Secretary of State under sections 1 and 4(1)(b) of the Climate Change Act 2008 (carbon targets and budgets);

(b)the interests of existing and future consumers of electricity, including their interests in relation to the cost and security of supply of electricity;

(c)costs, expenditure or liabilities of any description that the nuclear company may reasonably be expected to incur in carrying out its activities;

(d)the need to secure that the nuclear company is able to finance its activities;

(e)the need to secure that the nuclear company has appropriate incentives in relation to the carrying out of its activities;

(f)such other matters as the Secretary of State considers appropriate.

(5)Modifications made under subsection (1)(a) may include, for example—

(a)provision about the revenue that the nuclear company may receive in respect of its activities (the company’s “allowed revenue”);

(b)provision about how the nuclear company’s allowed revenue is to be calculated;

(c)provision about the amounts that the nuclear company is entitled to receive, or is required to pay, under any revenue collection contract to which it is a party;

(d)provision about activities that the nuclear company must, may or may not carry on;

(e)provision about the management of the nuclear company’s activities, including the manner in which they are carried out;

(f)provision conferring functions on the Authority, including provision enabling or requiring the nuclear company to refer for determination, decision or approval by the Authority matters specified, or of a description specified, in the licence;

(g)provision enabling the nuclear company to refer to the CMA a decision of the Authority falling within section 10(3) (decisions relating to allowed revenue);

(h)provision for the amendment of the licence for the purpose of implementing a determination or decision of the Authority or the CMA;

(i)provision requiring the nuclear company to comply with any direction or instruction, or to have regard to any guidance, given by the Authority in relation to matters specified, or of a description specified, in the licence;

(j)provision requiring the nuclear company to co-operate with the Authority and to provide such information and assistance to the Authority as the Authority may require for the purposes of carrying out any of its functions;

(k)provision about the payment by the nuclear company, to the Authority or to the CMA, of such amounts as may be determined by or in accordance with the licence;

(l)provision about relevant licensee nuclear company administration orders (as defined in section 31(1)), including provision about the raising of funds for the purpose of meeting expenses arising by virtue of such an order;

(m)provision about the disclosure or publication of information by the nuclear company.

(6)Modifications made under subsection (1)(b) may include, for example, provision relating to the circumstances in which the nuclear company’s electricity generation licence may be revoked.

(7)The Secretary of State may modify—

(a)the standard conditions incorporated in licences under section 6(1)(a) to (d) of the Electricity Act 1989 by virtue of section 8A of that Act;

(b)a document maintained in accordance with the conditions of licences under section 6(1)(a) to (d) of the Electricity Act 1989 or an agreement that gives effect to a document so maintained.

(8)The Secretary of State may exercise the power under subsection (7) only if the Secretary of State considers it appropriate to do so in consequence of, or for purposes incidental or supplementary to, the making of a modification under subsection (1).

(9)Modifications made under subsection (1) or (7) do not take effect unless the nuclear company whose licence is modified under subsection (1) enters into a revenue collection contract with a revenue collection counterparty.

(10)References in this section to the activities of a nuclear company are references to the company’s activities in relation to the design, construction, commissioning and operation of the nuclear project, including its activities in complying with any obligations it has under an approved funded decommissioning programme under Chapter 1 of Part 3 of the Energy Act 2008.

Commencement Information

I1S. 6 in force at 1.6.2022, see s. 44(2)(a)

7Licence modifications: relevant licensee nuclear companiesE+W+S

(1)The Secretary of State may modify a condition of a relevant licensee nuclear company’s electricity generation licence.

(2)The Secretary of State may exercise the power under subsection (1) only if the Secretary of State considers that—

(a)the total expenditure expected to be incurred by the relevant licensee nuclear company in order to complete the construction of the nuclear project is likely to exceed any cap on such expenditure included in the licence, and

(b)in consequence of paragraph (a), an adjustment is needed in relation to how the company’s allowed revenue is to be calculated.

(3)When exercising the power under subsection (1), the Secretary of State must have regard to the matters mentioned in section 6(4).

(4)The power under subsection (1) may not be exercised in relation to a relevant licensee nuclear company at any time after construction of the nuclear project has been completed.

(5)For the purposes of this section, construction of the nuclear project is to be taken to have been completed on successful completion of such procedures and tests relating to the project as constitute, at the time they are undertaken, the usual industry standards and practices for nuclear energy generation projects in order to demonstrate that they are capable of commercial operations.

(6)The Secretary of State must publish a statement setting out the procedure that the Secretary of State expects to follow in determining whether to exercise the power under subsection (1).

Commencement Information

I2S. 7 in force at 1.6.2022, see s. 44(2)(a)

8Procedure etc relating to modifications under section 6 or 7E+W+S

(1)Before making a modification under a power conferred by section 6(1) or (7) or 7(1) (a “relevant power”), the Secretary of State must consult—

(a)the nuclear company whose licence is being modified,

(b)the Authority,

(c)the Office for Nuclear Regulation,

(d)where any part of the site for the nuclear project is in England, the Environment Agency,

(e)where any part of the site for the nuclear project is in Wales, the Welsh Ministers and Natural Resources Wales,

(f)where any part of the site for the nuclear project is in Scotland, the Scottish Ministers and the Scottish Environment Protection Agency,

(g)in the case of a modification under section 6(7), other holders of a licence being modified, and

(h)such other persons as the Secretary of State considers appropriate.

(2)In the case of the exercise of a power conferred by section 6(1) or (7), subsection (1) may be satisfied by consultation before the passing of this Act (as well as by consultation after that time).

(3)A relevant power—

(a)may be exercised generally, only in relation to specified cases, or subject to exceptions (including provision for a case to be excepted only so long as specified conditions are satisfied);

(b)may be exercised differently for different purposes;

(c)includes power to make incidental, supplementary, consequential or transitional modifications.

(4)Provision included in a licence, or in a document or agreement described in section 6(7)(b), by virtue of a relevant power—

(a)may make different provision for different purposes;

(b)need not relate to the activities authorised by the licence;

(c)may do anything authorised for licences of that type by section 7(4), (5)(a) or (6A) of the Electricity Act 1989.

(5)The Secretary of State must publish details of any modifications made under a relevant power as soon as reasonably practicable after they are made.

(6)If under section 6(7) the Secretary of State makes a modification of the standard conditions of a licence, the Authority must—

(a)make the same modification of those standard conditions for the purposes of their incorporation in licences of that type granted after that time, and

(b)publish the modification.

(7)A modification made under a relevant power of part of a standard condition of a licence does not prevent any other part of the condition from continuing to be regarded as a standard condition for the purposes of Part 1 of the Electricity Act 1989.

(8)The power conferred by a relevant power to “modify” (in relation to licence conditions or terms or a document or agreement) includes power to amend, add to or remove; and references to modifications are to be construed accordingly.

Commencement Information

I3S. 8 in force at 1.6.2022, see s. 44(2)(a)

9Expiry of modifications made under section 6E+W+S

(1)This section applies if the designation of a nuclear company under section 2(1) ceases to have effect in accordance with—

(a)section 4(1)(a) (expiry of designation), or

(b)section 5(1) or (3) (revocation or lapse of designation).

(2)Any modifications made under section 6(1) of the nuclear company’s electricity generation licence are to be treated, from the relevant time, as not having been made.

(3)If any modifications of licences were made under section 6(7) in consequence of, or for purposes incidental or supplementary to, the modification under section 6(1) of the nuclear company’s electricity generation licence, those modifications are to be treated, from the relevant time, as not having been made.

(4)In subsections (2) and (3), “the relevant time” means the time when the designation of the nuclear company ceases to have effect.

(5)Where modifications are to be treated by subsection (2) or (3) as not having been made, the Secretary of State must publish details of that fact.

Commencement Information

I4S. 9 in force at 1.6.2022, see s. 44(2)(a)

10Decisions relating to allowed revenue of relevant licensee nuclear company: appeals to CMAE+W+S

(1)This section applies where a relevant licensee nuclear company’s electricity generation licence contains provision referred to in section 6(5)(g) (provision enabling company to refer decisions of the Authority to the CMA).

(2)Sections 11C to 11H of, and Schedule 5A to, the Electricity Act 1989 (appeal to the CMA against a decision by the Authority) apply in relation to a decision falling within subsection (3) below as they apply in relation to a decision mentioned in section 11C(1) of that Act.

(3)A decision falls within this subsection if—

(a)the decision is made by the Authority in the exercise of its functions relating to the regulation of a relevant licensee nuclear company,

(b)in the CMA’s opinion, the decision relates to the allowed revenue of the company, and

(c)but for this section, the company could not under section 11C of the Electricity Act 1989 bring an appeal against the decision.

(4)In the application of the provisions of the Electricity Act 1989 mentioned in subsection (2)

(a)section 11C has effect as if for subsection (2) there were substituted—

(2)An appeal may be brought under this section only by a relevant licensee nuclear company (within the meaning of Part 1 of the Nuclear Energy (Financing) Act 2022).;

(b)section 11E (4) (d) is to be ignored;

(c)sections 11F and 11G apply to a decision falling within subsection (3) as they apply to a price control decision as defined by section 11F(7);

(d)paragraph 1 of Schedule 5A has effect as if for sub-paragraph (3) there were substituted—

(3)Any application for permission to appeal is not to be made after the end of 20 working days beginning with the first working day after the day on which the Authority notifies its decision to the relevant licensee nuclear company.;

(e)paragraph 2 of Schedule 5A has effect as if, in sub-paragraph (2)(c), for the words from the beginning to “(as the case may be)” there were substituted “the relevant licensee nuclear company”.

Commencement Information

I5S. 10 in force at 1.6.2022, see s. 44(2)(a)

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources