- Latest available (Revised)
- Original (As enacted)
This version of this provision is prospective.![]()
The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:
Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.
There are outstanding changes not yet made by the legislation.gov.uk editorial team to Neighbourhood Planning Act 2017. Any changes that have already been made by the team appear in the content and are referenced with annotations.![]()
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
Prospective
(1)This section applies where a person (a “claimant”) to whom compensation is or will be payable under section 23 makes a request in accordance with subsection (3).
(2)The acquiring authority—
(a)must make an advance payment on account of the compensation if it has given a notice of intended entry under section 20 in relation to the land in respect of which the claimant is or will be entitled to compensation, but
(b)may not do so if it has not given such a notice.
(3)A request for advance payment must be made in writing by the claimant and must include—
(a)details of the basis on which the claimant is or is going to be entitled to compensation, and
(b)information which is sufficient to enable the acquiring authority to estimate the amount of the compensation in respect of which the advance payment is to be made.
(4)Before the end of the period of 28 days beginning with the day on which the acquiring authority receives a request under subsection (3), the authority must—
(a)determine whether it has enough information to estimate the amount of compensation, and
(b)if it needs more information, require the claimant to provide it.
(5)The amount of an advance payment is to be equal to 90% of—
(a)if the acquiring authority and the claimant have agreed on the amount of the compensation, the agreed amount, or
(b)in any other case, an amount equal to the compensation as estimated by the acquiring authority.
(6)An advance payment must be made—
(a)before the end of the day on which the authority takes temporary possession of the land, or
(b)if later, before the end of the period of two months beginning with the day on which the authority—
(i)receives the request for the advance payment, or
(ii)receives any further information required under subsection (4)(b).
(7)If, after making an advance payment on the basis of its estimate of the compensation, the acquiring authority considers that its estimate was too low, the authority must pay the claimant the balance of the amount of the advance payment calculated on the basis of the authority's new estimate of the compensation.
(8)Where the total amount of any payments under this section made on the basis of the acquiring authority's estimate of the compensation exceeds the compensation as finally determined or agreed, the excess is to be repaid.
(9)If, after a payment under this section has been made to a person, it is discovered that the person was not entitled to it, the person must repay it.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: