SCHEDULES

SCHEDULE 3Sustainable Drainage

Applications for approval

I1I28

1

This paragraph provides two approaches for applying for approval required by paragraph 7.

2

If the construction work does not require planning permission, the application for approval under paragraph 7 must be made in accordance with paragraph 9.

3

If the construction work requires planning permission, the application for approval under paragraph 7 may be—

a

made in accordance with paragraph 9, or

b

combined with the application for planning permission in accordance with paragraph 10.

4

Planning permission” means planning permission under the Town and Country Planning Act 1990.