Search Legislation

Energy Act 2008

Modification of approved programmes
Section 48: Modification of approved programme

242.This section allows for a funded decommissioning programme to be modified once it has been approved, and allows for the modification of any condition attached to the programme. This section gives the Secretary of State flexibility to amend a decommissioning programme, for example to reflect advances in decommissioning technologies or where cost estimates change.

243.Subsections (1) and (2) provide that the Secretary of State, the site operator and any other person who has obligations under the programme can propose a modification to the programme. Where a modification is proposed by a person who falls into the last category it requires the consent of the site operator.

244.Subsection (3) allows obligations or additional obligations to be placed on (or removed from) bodies corporate associated with the operator, such as a parent company. Subsection (4) enables a modification to be made which places conditions on the approval even if the funded decommissioning programme was originally approved unconditionally.

Section 49: Procedure for revising approved programme

245.This section establishes the procedure for making a modification to an approved funded programme. Subsection (1) makes it clear that this section is subject to regulations made under section 50.

246.Subsection (2) requires a proposal to make a modification to be in writing. If the proposal is made by the Secretary of State, written notice must be given to the site operator. If the proposal is made by any other person, written notice must be given to the Secretary of State.

247.Subsections (3) and (4) allow the Secretary of State to charge the site operator a fee in relation to the consideration of the proposal, and, in particular, the costs of obtaining advice in relation to the proposal or in relation to information required in relation to the proposal in accordance with section 52(4). The manner in which this fee is to be calculated and the time for its payment are to be set out in regulations under section 54.

248.Subsection (5) states that the operator or any other person with obligations under a programme (or who would have obligations as a result of the proposed modification), must be given the opportunity to respond in writing to any proposal by the Secretary of State to make a modification.

249.Subsection (6) gives the Secretary of State the power to decide whether a modification should be made. The Secretary of State must give notice of the decision and reasons for it to every person who has obligations under the programme or will have obligations as a result of the modification. Under subsection (7), any decision as to whether to make a modification must be made with the aim of securing that prudent provision is made for the technical matters (including the financing of the designated technical matters).

250.Subsection (8) requires the Secretary of State, before deciding whether to make a modification, to consult with the Health and Safety Executive, the Environment Agency, and the Department of the Environment for Northern Ireland.

Section 50: Power to disapply section 49

251.This section provides the Secretary of State with the power to make regulations, (subject to the negative resolution procedure - see section 105), to disapply section 49 in relation to modifications proposed by a person other than the Secretary of State, as set out in subsection (1).

252.Before making any such regulations, the Secretary of State must consult with the Health and Safety Executive, the Environment Agency and the Department of the Environment for Northern Ireland.

253.Subsection (3) allows regulations under subsection (1) to categorise modifications by reference to their financial consequences, including by reference to the cumulative financial effect of a number of modifications over a given period. Regulations might, therefore, set out that any operational changes which have a financial impact below a certain amount within a specified period of time are to be exempt from the requirements of section 49).

254.Subsection (4) provides that when the site operator modifies the plan in accordance with the regulations (so that the modification procedure in section 49 does not apply), it must notify the Secretary of State in the manner specified in the regulations.

Section 51: Time when modification takes effect

255.This section sets out when a modification to a funded decommissioning programme takes effect. Where a modification is made in line with the process set out in section 49, the modification takes effect at the time specified in the notice given to the operator of the Secretary of State’s decision that the modification is to be made. That time must not be before that notice is given (subsection (4)).

256.Where a modification is made by a site operator under regulations disapplying the standard process (i.e. in line with subsection (1) of section 50), the modification takes effect at the time specified in the notice given by the operator to the Secretary of State in the manner set out in the regulations made under section 54. The time specified in the notice cannot be earlier than the time when the notice is given (subsection (4)).

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item