The Authority’s functions in relation to applications
211.Paragraph 12 contains provisions governing the Authority’s consideration of an application. The Authority must consider the application on the basis of whether a property scheme is necessary or expedient for the performance of the successful bidder’s functions as offshore transmission licence holder. The paragraph also sets out a procedure for the Authority to propose alternative arrangements in cases where it decides that the proposed treatment of particular property, rights or liabilities is not necessary or expedient, but that some other kind of provision should be made. For example, the Authority might decide that transfer of ownership of a particular piece of equipment was not justified, as the granting of access rights would be sufficient. Before making alternative arrangements, the Authority must inform the parties and affected third parties, who have the opportunity to make representations to the Authority on the proposal.
212.In order to ensure that property is not transferred prematurely, paragraph 13 provides that the Authority may not make a scheme until:
the offshore transmission licence has been awarded to the successful bidder; and
the System Operator (described as the co-ordination licence holder in the Schedule) issues a notice of completion to the Authority in respect of the relevant transmission system. (Some large projects are being built in phases, with a working transmission system being in place as each phase of the generating station is completed, so that electricity can be transmitted to shore as and when each phased part of the project is ready. For such projects, it is envisaged that separate completion notices might be issued in respect of the transmission systems in place for each phase (and ultimately form part of a larger transmission system for the entire project once all phases had been completed).