xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"
Textual Amendments
F1Words in Sch. 3 title substituted (12.4.2015) by Infrastructure Act 2015 (c. 7), ss. 32(3), 57(5)(e) (with s. 32(11)(12))
Modifications etc. (not altering text)
C1Sch. 3 applied by 2011 c. 20, s. 208(1) (as substituted (13.7.2016) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 19 para. 17; S.I. 2016/733, reg. 3(m))
C2Sch. 3 applied by 1999 c. 29, s. 333ZB(1) (as substituted (13.7.2016) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 19 para. 12(2); S.I. 2016/733, reg. 3(m) (with reg. 10))
C3Schs. 2-4 applied (with modifications) (17.3.2017) by The Liverpool City Region Combined Authority (Functions and Amendment) Order 2017 (S.I. 2017/430), arts. 1(2), 9(3), Sch. 3 Pt. 2
4(1)This paragraph applies if the Secretary of State is proposing to make an order under paragraph 3.E+W
(2)The Secretary of State must—
(a)publish a notice stating—
(i)the effect of the order,
(ii)the time (not less than 28 days starting with the date of publication of the notice) within which objections to the proposal may be made, and
(iii)the manner in which objections to the proposal may be made, and
(b)serve a copy of the notice on—
(i)the local planning authority in whose area the land is situated, and
(ii)the relevant highway authority.
(3)In sub-paragraph (2) “the relevant highway authority” means any authority which is a highway authority in relation to the right of way which is proposed to be extinguished by the order.
(4)Publication under sub-paragraph (2) must be in such manner as the Secretary of State considers appropriate.
Commencement Information
I1Sch. 3 para. 4 in force at 1.12.2008 by S.I. 2008/3068, art. 2(1)(f) (with arts. 6-13)