SCHEDULES

SCHEDULE 15 Protective Provisions

C1Part VII Protection of Port of London Authority

Annotations:
Modifications etc. (not altering text)
C1

Sch. 15 Pt. VII (paras. 1-10) applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 paras. 1(j), 3(10)

1

1

The provisions of this Part of this Schedule shall, unless otherwise agreed in writing between the nominated undertaker and the Port Authority, have effect for the protection of the Port Authority and the users of the river.

2

In this Part of this Schedule—

  • construction” includes execution, placing, altering, replacing, relaying and removal and, in its application to works which include or comprise any operation, means the carrying out of that operation;

  • operations” includes temporary works, dredging and mooring of vessels authorised by paragraph 11 of Schedule 2 to this Act;

  • plans” includes sections, drawings, specifications and method statements;

  • the Port Authority” means the Port of London Authority;

  • the river” means the waters within the limits of the port of London as described in Schedule 1 to the M1Port of London Act 1968;

  • specified work” means so much of any permanent or temporary work authorised by Part I of this Act (which includes, for the avoidance of doubt, any removal of gravel or other material, any dredging or similar work and any geotechnical investigations that may be undertaken) as is on, in, under or over—

    1. a

      the surface of land below the level of mean high water springs forming part of the river; or

    2. b

      any land owned, occupied or used by the Port Authority for operational purposes.