xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 15U.K. Protective Provisions

Part IIIU.K. Protection of Land Drainage, Flood Defence, Water Resources and Fisheries

Modifications etc. (not altering text)

C1Sch. 15 Pt. III (ss. 1-12) applied (with modifications) (19.2.1999) by S.I. 1999/537, art. 13(1), Sch. 3 paras. 1-8

Sch. 15 Pt. III (paras. 1-12) applied (with modifications) (22.3.2001) by S.I. 2001/1451, art. 15(1), Sch. 3 para. 1(j)

Sch. 15 Pt. III applied (with modifications) (12.8.2002) by S.I. 2002/1943, art. 15(1)(d)

3U.K.The requirements which the Agency may make under paragraph 2 above include conditions requiring the nominated undertaker at its own expense to construct such protective works (including any new works as well as alterations to existing works) as are reasonably necessary—

(a)to safeguard any drainage work against damage, or

(b)to secure that its efficiency for flood defence purposes is not impaired,

during the construction of the specified work.