9(1)Subject to sub-paragraph (2) below, if at any time a survey under paragraph 5(3) or (4) above shows that the building has suffered or is likely to suffer groundwater damage, that building shall, for the purposes of this Schedule, be treated from the day when the survey report is received by the Development Corporation as if it were a building within the protected property area.
(2)Where—
(a)the survey is under paragraph 5(4)(a) above, or
(b)the survey is under paragraph 5(4)(b) above and a survey of the building has previously been carried out under paragraph 5(4)(a) above,
paragraph 4(2) above shall not apply in relation to the building by virtue of sub-paragraph (1) above.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: