Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Restrictions on abstraction and impoundingE+W

24 Restrictions on abstraction.E+W

(1)Subject to the following provisions of this Chapter and to any drought order [F1or drought permit] under Chapter III of this Part, no person shall—

(a)abstract water from any source of supply; or

(b)cause or permit any other person so to abstract any water,

except in pursuance of a licence under this Chapter granted by the [F2appropriate agency] and in accordance with the provisions of that licence.

(2)Where by virtue of subsection (1) above the abstraction of water contained in any underground strata is prohibited except in pursuance of a licence under this Chapter, no person shall begin, or cause or permit any other person to begin—

(a)to construct any well, borehole or other work by which water may be abstracted from those strata;

(b)to extend any such well, borehole or other work; or

(c)to instal or modify any machinery or apparatus by which additional quantities of water may be abstracted from those strata by means of a well, borehole or other work,

unless the conditions specified in subsection (3) below are satisfied.

(3)The conditions mentioned in subsection (2) above are—

(a)that the abstraction of the water or, as the case may be, of the additional quantities of water is authorised by a licence under this Chapter; and

(b)that—

(i)the well, borehole or work, as constructed or extended; or

(ii)the machinery or apparatus, as installed or modified,

fulfils the requirements of that licence as to the means by which water is authorised to be abstracted.

(4)A person shall be guilty of an offence if—

(a)he contravenes subsection (1) or (2) above; or

(b)he is for the purposes of this section the holder of a licence under this Chapter and, in circumstances not constituting such a contravention, does not comply with a condition or requirement imposed by the provisions, as for the time being in force, of that licence.

(5)A person who is guilty of an offence under this section shall be liable [F3on summary conviction, or on conviction on indictment, to a fine].

(6)The restrictions imposed by this section shall have effect notwithstanding anything in any enactment contained in any Act passed before the passing of the M1Water Resources Act 1963 on 31st July 1963 or in any statutory provision made or issued, whether before or after the passing of that Act, by virtue of such an enactment.

Textual Amendments

F1By S.I. 1996/593, reg. 3, Sch. 2 para. 8 it is provided that the words “or drought permit” be substituted (1.4.1996) for the words following “drought order”

Modifications etc. (not altering text)

C5S. 24(1) restricted (16.3.1992) by Aire and Calder Navigation Act 1992 (c. iv), s. 17(2)

C6S. 24(1) restricted (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 14 para. 15

Marginal Citations

[F424AAbstraction licencesE+W

(1)Each licence to abstract water shall be of one of the following three types—

(a)a licence to abstract water from one source of supply over a period of twenty-eight days or more for any purpose (a “full licence”);

(b)a licence to abstract water from one source of supply over a period of twenty-eight days or more for the purpose of—

(i)transferring water to another source of supply; or

(ii)transferring water to the same source of supply, but at another point, in the course of dewatering activities in connection with mining, quarrying, engineering, building or other operations (whether underground or on the surface),

in either case without intervening use (a “transfer licence”);

(c)a licence to abstract water from one source of supply over a period of less than twenty-eight days (a “temporary licence”).

(2)In this Act, a reference (however expressed) to a licence to abstract water is to be taken as a reference to all types of licence, unless it is clear that a different meaning is intended.]

Textual Amendments

25 Restrictions on impounding.E+W

[F5(1)Subject to the following provisions of this Chapter and to any drought order or drought permit under Chapter 3 of this Part, no person shall—

(a)begin, or cause or permit any other person to begin, to construct or alter any impounding works at any point in any inland waters which are not discrete waters; or

(b)cause or permit the flow of any inland waters which are not discrete waters to be obstructed or impeded at any point by means of impounding works,

unless (in either case) the conditions mentioned in subsection (1A) below are satisfied.

(1A)The conditions are—

(a)a licence under this Chapter granted by the [F6appropriate agency] to obstruct or impede the flow of those inland waters at that point by means of impounding works is in force;

(b)the impounding works will not (or, as the case may be, do not) obstruct or impede the flow of the inland waters except to the extent, and in the manner, authorised by the licence; and

(c)any other conditions or requirements imposed by the provisions, as for the time being in force, of the licence (whether as to the provision of compensation water or otherwise) are complied with.]

(2)A person shall be guilty of an offence if—

(a)he contravenes subsection (1) above; or

(b)he is for the purposes of this section the holder of a licence under this Chapter and F7... does not comply with a condition or requirement imposed by the provisions, as for the time being in force, of that licence.

(3)A person who is guilty of an offence under this section shall be liable [F8on summary conviction, or on conviction on indictment, to a fine].

(4)Subject to subsection (5) below, the restrictions imposed by this section shall have effect notwithstanding anything in any enactment contained in any Act passed before the passing of the M2Water Resources Act 1963 on 31st July 1963 or in any statutory provision made or issued, whether before or after the passing of that Act, by virtue of such an enactment.

(5)Subject to subsection (6) below, the restriction on impounding works [F9shall not apply in respect of any impounding works], if—

(a)the construction or alteration of those works; or

(b)the obstruction or impeding of the flow of the inland waters resulting from the construction or alteration of the works,

is authorised (in whatsoever terms, and whether expressly or by implication) by virtue of any such statutory provision as at the coming into force of this Act was an alternative statutory provision for the purposes of section 36(2) of the Water Resources Act 1963.

(6)The provisions of this Chapter shall have effect in accordance with subsection (7) below where by virtue of any such provision as is mentioned in subsection (5) above and is for the time being in force—

(a)any water undertaker or sewerage undertaker to which rights under that provision have been transferred in accordance with a scheme under Schedule 2 to the M3Water Act 1989 or Schedule 2 to the M4Water Industry Act 1991; or

(b)any other person,

is authorised (in whatsoever terms, and whether expressly or by implication) to obstruct or impede the flow of any inland waters by means of impounding works (whether those works have already been constructed or not).

(7)Where subsection (6) above applies, the provisions of this Chapter shall have effect (with the necessary modifications), where the reference is to the revocation or variation of a licence under this Chapter, as if—

(a)any reference in those provisions to a licence under this Chapter included a reference to the authorisation mentioned in that subsection; and

(b)any reference to the holder of such a licence included a reference to the undertaker or other person so mentioned.

(8)In this Chapter “impounding works” means either of the following, that is to say—

(a)any dam, weir or other works in any inland waters by which water may be impounded;

(b)any works for diverting the flow of any inland waters in connection with the construction or alteration of any dam, weir or other works falling within paragraph (a) above.

[F10(9)In relation to impounding works, references to alteration include the removal or partial removal of those works, and cognate expressions shall be construed accordingly.]

Textual Amendments

F5S. 25(1)(1A) substituted for s. 25(1) (1.4.2006) by Water Act 2003 (c. 37), ss. 2(2), 105(3) (with s. 2(10)); S.I. 2006/984, art. 2(b) (with Sch. para. 2)

F7Words in s. 25(2) repealed (1.4.2006) by Water Act 2003 (c. 37), ss. 2(3), 105(3), Sch. 9 Pt. 1 (with s. 2(10)); S.I. 2006/984, art. 2(b)(s)(ii) (with Sch. para. 2)

F9Words in s. 25(5) substituted (1.4.2006) by Water Act 2003 (c. 37), ss. 2(4), 105(3) (with s. 2(10)); S.I. 2006/984, art. 2(b) (with Sch. para. 2)

Modifications etc. (not altering text)

C22S. 25(1)(b) modified (1.4.2006) by Water Act 2003 (c. 37), ss. 3, 105(3); S.I. 2006/984, art. 2(c) (with Sch. para. 2)

Marginal Citations

[F1125AEnforcement noticesE+W

(1)Subject to the following provisions of this section, where it appears to the [F12appropriate agency] that a person is—

(a)in breach of section 24(1) or (2) or section 25(1) above; or

(b)for the purposes of section 24 or 25 above a holder of a licence under this Chapter and has not complied with a condition or requirement imposed by the provisions, as for the time being in force, of that licence,

the [F12appropriate agency] shall be entitled to serve an enforcement notice on him if the condition in subsection (2) below is satisfied.

(2)The condition is that it appears to the [F12appropriate agency] that the breach or failure to comply is causing or is likely to cause significant damage to the environment.

(3)An enforcement notice is a notice requiring the person on whom it is served—

(a)to cease his breach of section 24(1) or (2) or section 25(1) above, or to comply with the condition or requirement in question; and

(b)to carry out any works or operations specified in the notice.

(4)The works or operations which may be specified are works or operations which it appears to the [F12appropriate agency] are appropriate for the purpose of remedying or mitigating the effects of the breach or failure to comply, and may include—

(a)works or operations for the purpose, so far as it is reasonably practicable to do so, of restoring any affected waters, including any flora and fauna dependent on them, to their state immediately before the breach or failure to comply; and

(b)in the case of a breach of section 25(1) above, the removal of any unauthorised impounding works or the reversal of any unauthorised alteration to impounding works.

(5)An enforcement notice must specify the periods within which the person on whom it is served must do each of the things specified in the notice.

(6)Before serving an enforcement notice on any person, the [F12appropriate agency] shall take reasonable steps to consult that person about the works or operations which are to be specified in the notice.

(7)The Secretary of State may by regulations make provision for or in connection with—

(a)the form or content of enforcement notices;

(b)requirements for consultation, before the service of an enforcement notice, with persons other than the person upon whom the notice is to be served;

(c)steps to be taken for the purposes of any consultation required under subsection (6) above or regulations made by virtue of paragraph (b) above;

(d)any other steps of a procedural nature which are to be taken in connection with, or in consequence of, the service of an enforcement notice.

(8)An enforcement notice is not invalid, or invalidly served, merely because of a failure to comply with subsection (6) above or with regulations made by virtue of subsection (7)(b) above.

(9)The Secretary of State may, if he thinks fit in relation to any person, give directions to the [F12appropriate agency] as to whether or how it should exercise its powers under this section.

(10)In proceedings for any offence under section 24 or 25 above against a person upon whom an enforcement notice has been served, the following are not to be taken as evidence that he has committed the offence—

(a)the fact that an enforcement notice has been served on him;

(b)the fact that he does not appeal against it;

(c)the fact that on an appeal against it the notice is confirmed (whether with or without modifications).

Textual Amendments

F11Ss. 25A-25C inserted (1.4.2006) by Water Act 2003 (c. 37), ss. 30, 105(3); S.I. 2006/984, art. 2(o)

Modifications etc. (not altering text)

C24Ss. 25A(5)-(9) applied (with modifications) (1.4.2006) by Water Act 2003 (c. 37), ss. 4(3)(a), 105(3); S.I. 2006/984, art. 2(d)

25BRights of entry and appealsE+W

Sections 161B and 161C below (including any power to make regulations) shall apply in relation to enforcement notices as they apply in relation to works notices under section 161A below.

Textual Amendments

F11Ss. 25A-25C inserted (1.4.2006) by Water Act 2003 (c. 37), ss. 30, 105(3); S.I. 2006/984, art. 2(o)

Modifications etc. (not altering text)

25CConsequences of not complying with an enforcement noticeE+W

(1)If a person on whom the [F13appropriate agency] serves an enforcement notice fails to comply with any of its requirements, he shall be guilty of an offence.

(2)A person who commits an offence under subsection (1) above shall be liable [F14on summary conviction, or on conviction on indictment, to a fine].

(3)If a person on whom an enforcement notice has been served fails to comply with any of its requirements, the [F13appropriate agency] may do what that person was required to do and may recover from him any costs or expenses reasonably incurred by the [F13appropriate agency] in doing it.

(4)If the [F13appropriate agency] is of the opinion that proceedings for an offence under subsection (1) above would afford an ineffectual remedy against a person who has failed to comply with the requirements of an enforcement notice, the [F13appropriate agency] may take proceedings in the High Court for the purpose of securing compliance with the notice.]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources