SCHEDULES

C1 SCHEDULE 4 Streets with special engineering difficulties

Annotations:
Modifications etc. (not altering text)
C1

Sch. 4 modified (27.11.1992) by S.I. 1992/2984, art. 3(2)

Requirement of plan and section

2

1

In a street with special engineering difficulties street works (other than emergency works) involving—

a

breaking up or opening the street, or any sewer, drain or tunnel under it, or

b

tunnelling or boring under the street,

shall not be executed until a plan and section of the works have been settled by agreement between the undertaker and each of the relevant authorities or by arbitration.

2

For that purpose an undertaker proposing to execute any such works shall submit a plan and section of them to each relevant authority.