xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

Part IIIE+W Control over development

Modifications etc. (not altering text)

C1Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11

Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3

Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)

Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51

Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)

Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4

Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))

Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2

Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)

Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)

C4Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)

Duration of planning permissionE+W

[F193AExtension of certain planning permissions: automatic extensionE+W

(1)This section applies in relation to relevant planning permission granted or deemed to be granted—

(a)in relation to the development of land in England, and

(b)subject to a condition which has the effect that the development to which the permission relates must be begun not later than a time falling within the period—

(i)beginning with the day on which section 17 of the Business and Planning Act 2020 comes into force, and

(ii)ending with 31 December 2020.

(2)The condition is deemed to provide instead that the development to which the relevant planning permission relates must be begun not later than 1 May 2021.

(3)The time by which the development to which the relevant planning permission relates must be begun is not to be extended (whether by section 91(3B) or otherwise) to a later time than that for the time being provided for in subsection (2).

(4)The reference in subsection (1) to relevant planning permission being granted, or deemed to be granted, subject to a condition which has the effect mentioned in paragraph (b) of that subsection includes a reference to the permission being subject to a condition which has that effect by virtue of being subsequently modified (whether by section 91(3B) or otherwise).]

Textual Amendments

F1Ss. 93A-93C inserted (temp.) (19.8.2020) by virtue of Business and Planning Act 2020 (c. 16), ss. 17(2), 25(3)(b) (with s. 17(6))

Modifications etc. (not altering text)

C12S. 93A(1)(b)(ii): power to amend conferred (19.8.2020) by Business and Planning Act 2020 (c. 16), ss. 17(7)(a), 25(3)(b)

C13S. 93A(2): power to amend conferred (19.8.2020) by Business and Planning Act 2020 (c. 16), ss. 17(7)(a), 25(3)(b)