C1C2C3C4C5C6C7C8C9 Part III Control over development

Annotations:
Modifications etc. (not altering text)
C1

Pt. 3 (ss. 55-106) except ss. 76, 90(2)(5) applied (with modifications) (17.7.1992) by S.I. 1992/1492, regs. 2(1)(b), 3-11

Pt. 3 (ss. 55-106): power to modify conferred (10.11.1993) by 1993 c. 28, s. 171(1)(a); S.I. 1993/2762, art. 3

Pt. 3 (ss. 55-106) applied (5.11.1993) by 1993 c. 42, s. 24(1) (with ss. 2, 30(1), Sch. 2 para.9)

Pt. 3 (ss. 55-106) extended (1.11.1995) by 1995 c. 25, s. 96(2) (with ss. 7(6), 115, 117); S.I. 1995/2765, art. 2

Pt. 3 (ss. 55-106) modified (1.4.1996) by 1994 c. 19, s. 20(3), Sch. 5 Pt. III paras. 15(1), 20 (with ss. 54(5)(7), 55(5), Sch. 17 paras. 22(1), 23(2)); S.I. 1995/3198, art. 4, Sch. 2

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 9(1)(2)

Pt. 3 (ss. 55-106) modified (18.12.1996) by 1996 c. 61, s. 51

Pt. 3 (ss. 55-106) modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 20(1)

Pt. 3 (ss. 55-106) modified (31.10.2005) by The London Thames Gateway Development Corporation (Planning Functions) Order 2005 (S.I. 2005/2721), art. 4

Pt. 3 (ss. 55-106) modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 21(1) (with arts. 3(5), 15(3))

Pt. 3 (ss. 55-106) applied (7.6.2006) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 89, 121, Sch. 4 para. 3(2) (with s. 111); S.I. 2006/1281, art. 2

Pt. 3 (ss. 55-106) modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 17(1) (with art. 43)

Pt. 3 (ss. 55-106) modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 18(1)

C4

Pt. 3 modified (22.7.2008) by Crossrail Act 2008 (c. 18), s. 10(1)

F1Local development orders

Annotations:
Amendments (Textual)
F1

Ss. 61A-61C and preceding cross-heading inserted (6.8.2004 for certain purposes, 10.5.2006 for E. and otherwise prosp.) by Planning and Compulsory Purchase Act 2004 (c. 5), ss. 40(1), 121 (with s. 111); S.I. 2004/2097, art. 2; S.I. 2006/ 1061, {art. 2}

61DF2Effect of revision or revocation of development order on incomplete development

1

A development order or local development order may include provision permitting the completion of development if —

a

planning permission is granted by the order in respect of the development, and

b

the planning permission is withdrawn at a time after the development is started but before it is completed.

2

Planning permission granted by a development order is withdrawn—

a

if the order is revoked;

b

if the order is amended so that it ceases to grant planning permission in respect of the development or materially changes any condition or limitation to which the grant of permission is subject;

c

by the issue of a direction under powers conferred by the order.

3

Planning permission granted by a local development order is withdrawn—

a

if the order is revoked under section 61A(6) or 61B(8);

b

if the order is revised in pursuance of paragraph 2 of Schedule 4A so that it ceases to grant planning permission in respect of the development or materially changes any condition or limitation to which the grant of permission is subject;

c

by the issue of a direction under powers conferred by the order.

4

The power under this section to include provision in a development order or a local development order may be exercised differently for different purposes.