xmlns:atom="http://www.w3.org/2005/Atom"

Part XIIIApplication of Act to Crown Land

Enforcement in respect of war-time breaches of planning control by Crown

302Enforcement in respect of war-time breaches of planning control by the Crown

(1)This section applies where during the war period—

(a)works not complying with planning control were carried out on land, or

(b)a use of land not complying with planning control was begun by or on behalf of the Crown.

(2)Subject to subsection (4), if at any time after the end of the war period there subsists in the land a permanent or long-term interest which is neither held by or on behalf of the Crown nor subject to any interest or right to possession so held, the planning control shall, so long as such an interest subsists in the land, be enforceable in respect of those works or that use notwithstanding—

(a)that the works were carried out or the land used by or on behalf of the Crown, or

(b)the subsistence in the land of any interest held by or on behalf of the Crown in reversion (whether immediate or not) expectant on the termination of that permanent or long-term interest.

(3)A person entitled to make an application under this subsection with respect to any land may apply at any time before the relevant date to an authority responsible for enforcing any planning control for a determination—

(a)whether works on the land carried out, or a use of the land begun, during the war period fail to comply with any planning control which the authority are responsible for enforcing, and

(b)if so, whether the works or use should be deemed to comply with that control.

(4)Where any works on land carried out, or use of land begun, during the war period remain or continues after the relevant date and no such determination has been given, the works or use shall by virtue of this subsection be treated for all purposes as complying with that control unless steps for enforcing the control have been begun before that date.

(5)Schedule 15 shall have effect for the purpose of making supplementary provision concerning the enforcement of breaches of planning control to which this section applies and the making and determination of applications under subsection (3).

(6)In this section and that Schedule—

(7)References in this section and that Schedule to non-compliance with planning control mean—

(a)in relation to works on land carried out, or a use of land begun, at a time when the land was subject to a resolution to prepare a scheme under the [1932 c. 48.] Town and Country Planning Act 1932, that the works were carried out or the use begun otherwise than in accordance with the terms of an interim development order or of permission granted under such an order;

(b)in relation to works on land carried out, or a use of land begun, at a time when the land was subject to such a scheme, that the works were carried out or the use begun otherwise than in conformity with the provisions of the scheme;

and references in this Act to compliance with planning control shall be construed accordingly.

(8)References in this section and that Schedule to the enforcement of planning control shall be construed as references to the exercise of the powers conferred by section 75 of the 1947 Act or by paragraph 34 of Schedule 24 to the 1971 Act (including that paragraph as it continues in effect by virtue of Schedule 3 to the [1990 c. 9.] Planning (Consequential Provisions) Act 1990).